岩溶地层大断面铁路隧道悬臂掘进机施工穿越上部既有建筑扰动规律研究
(1.同济大学土木工程学院地下建筑与工程系,上海 200092;2.同济大学 岩土及地下工程教育部重点实验室,上海 200092;3.中铁二院昆明勘察设计研究院有限责任公司,昆明 650200)
Study on the Disturbance Patterns of Roadheader Construction of Large-section Railway Tunnel Under-crossing Existing Buildings in Karst Stratum
(1. Department of Geotechnical Engineering College of Civil Engineering, Tongji University, Shanghai 200092;2. Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education, Tongji University, Shanghai 200092;3. Kunming Survey, Design and Research Institute Co. Ltd. of CREEC, Kunming 650200)
Download: PDF (4759KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 为探究岩溶地层中悬臂掘进机施工穿越既有上部建筑物的扰动规律,提出岩溶空腔单元提取算法,依托采用悬臂掘进机施工的某铁路隧道穿越工程建立穿越节点三维精细化有限元模型,研究悬臂掘进机施工过程中的地表沉降、建筑物角点沉降、倾斜率的发展规律,探讨岩溶填充质量对地表沉降槽的影响。结果表明:(1)受建筑物基础刚度的影响,穿越施工引起的地表沉降槽呈现分段特征,地表沉降在建筑物基础范围内近似线性分布,在建筑物基础范围外的分布符合Peck公式规律;(2)穿越施工过程中,既有建筑物角点沉降和倾斜率呈现三阶段变化趋势,对应悬臂掘进机三台阶施工过程;(3)岩溶空腔填充质量对地表沉降的影响呈阶段性变化趋势,当填充质量不足70%时,随填充质量增加,地表最大沉降减小;当填充质量大于70%后,地表最大沉降基本稳定。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
汪元冶1 丁文其1
2 杨进京3 乔亚飞1
2 丁文云3
关键词隧道穿越   岩溶地层   既有建筑   悬臂掘进机施工   数值模拟     
Abstract: To investigate the disturbance patterns caused by the railway tunnel excavated by the boom-type road? header, which crosses undere the existing surface structures in karst strata, a karst cavity unit extraction algorithm was proposed, the three-dimensional refined finite element model was established based on a roadheader-excavated railway tunnel project, the ground settlement, the settlement and tilt rate of the existing surface structure were analyzed, and the impact of karst filling quantity on surface settlement trough was explored. The results indicate that:(1) Due to the foundation stiffness of the existing surface structure, the settlement trough caused by the boom-type roadheader construction exhibits segmented characteristics: it is approximately linear under the building and conforms to Peck formula form outside the building; (2) During the under-crossing process, the settlement and tilt rate of the existing surface structure show a three-staged variation trend, corresponding to the three-stage construction of boom-type roadheader; (3) The impact of karst cavity filling quantity on surface settlement exhibits a staged trend: When the filling quantity is less than 70 %, the maximum surface settlement decreases with increasing filling quantity. When the filling quantity exceeds 70 %, the maximum surface settlement remains stable.
KeywordsTunnel crossing,   Karst stratum,   Existing buildings,   Boom-type roadheader excavation,   Numerical simu? lation     
基金资助:云南科技厅重点研发计划(202303AA080003);国家自然科学基金(52090083).
作者简介: 汪元冶(2000-),男,硕士研究生,主要从事隧道与地下工程方面的相关研究工作,E-mail:yuanye_wang@tongji.edu.cn. 通讯作者:乔亚飞(1990-),男,博士,副教授,主要从事隧道与地下工程方面的教学与科研工作,E?mail:yafei.qiao@tongji.edu.cn.
引用本文:   
汪元冶1 丁文其1, 2 杨进京3 乔亚飞1, 2 丁文云3 .岩溶地层大断面铁路隧道悬臂掘进机施工穿越上部既有建筑扰动规律研究[J]  现代隧道技术, 2024,V61(5): 274-284
WANG Yuanye1 DING Wenqi1, 2 YANG Jinjing3 QIAO Yafei1, 2 DING Wenyun3 .Study on the Disturbance Patterns of Roadheader Construction of Large-section Railway Tunnel Under-crossing Existing Buildings in Karst Stratum[J]  MODERN TUNNELLING TECHNOLOGY, 2024,V61(5): 274-284
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2024/V61/I5/274
 
没有本文参考文献
[1] 冯冀蒙1,2 宋佳黛1,2 王圣涛3 李艺飞1,2 张俊儒1,2 王好明4 汪 波1,2.填海地层特大断面隧道超长管棚变形控制 效能研究[J]. 现代隧道技术, 2025,62(4): 155-162
[2] 熊 颖1,2 张俊儒1,2 范子焱1,2 陈佳豪1,2 马荐驰1,2 陈鹏涛1,2 谭瑞锋3,4.层状软岩中爆破应力波传播与振动衰减特性研究[J]. 现代隧道技术, 2025,62(4): 122-131
[3] 罗志洋1 张春瑜2,3 王立川1,2,4,5 徐 烁1 李利平4 王倩倩5 刘志强6.TBM裂隙岩体隧洞涌水机制及注浆堵水研究[J]. 现代隧道技术, 2025,62(4): 145-154
[4] 周弋力1 封 坤1 郭文琦1 张亮亮2 李春林3.超大直径盾构隧道管片纵缝抗弯力学行为与损伤过程研究[J]. 现代隧道技术, 2025,62(4): 163-173
[5] 易 丹1 薛皓匀2 杨绍毅2 喻 波1 封 坤2 林 刚1.盾构隧道管片结构螺栓失效对横向地震响应的影响分析[J]. 现代隧道技术, 2025,62(4): 174-181
[6] 贾永刚1 郝子晗1 鲁卫东1 吴 帆1 阳卫卫2.钢纤维混凝土管片不同接头型式力学性能研究[J]. 现代隧道技术, 2025,62(4): 182-196
[7] 罗 龙1 朱开宬2 韩瑀萱3 蔡 东4 刘哲奇5 王 俊6.超大断面隧道施工工法优化研究 ——以天邛高速公路梨花山隧道工程为例[J]. 现代隧道技术, 2025,62(4): 273-282
[8] 胡云进1,,2,3 朱铭伟1,2,3 郜会彩1,2,3 任智豪1,2,3.地下水渗流对能源盾构隧道换热性能的影响[J]. 现代隧道技术, 2025,62(3): 50-59
[9] 李玉华1 高亚伟1 钟秋锋1 秦丽绚2 李俊杰2 程志明2 黄永辉2.不同掏槽孔角度下隧道楔形掏槽爆破效果研究[J]. 现代隧道技术, 2025,62(3): 108-116
[10] 李瀚源1,2 冯 劲1 郭洪雨1 谢雄耀2 周红升1 孙 飞1.海底盾构隧道双层衬砌结构联合承载力学特性研究[J]. 现代隧道技术, 2025,62(3): 126-138
[11] 苏 恒1 王士民1 朱旭红2 秦善良3.考虑空间效应的盾构刀具切削桩基主筋力学特征研究[J]. 现代隧道技术, 2025,62(3): 139-150
[12] 王帅帅1 傅一帆2,3 徐 勇1 史经峰1 郭 春2,3.通过接力风机进行风量分配的隧道施工风仓式通风参数研究[J]. 现代隧道技术, 2025,62(3): 240-248
[13] 邹育麟1, 2 刘 静1 汪 波2 陈子全2 谢作栋2 古 浩3 王楷越2.四川沿江高速公路隧道涌水突泥灾害成因分析及防治对策研究[J]. 现代隧道技术, 2025,62(3): 259-269
[14] 葛正辉1 郑建国1 李新志2 陈 鹏3 宁志玮2 王鹏程2.不同形式拱架初期支护变形规律实测与数值研究[J]. 现代隧道技术, 2025,62(3): 40-49
[15] 李 敬1 罗禄森1 张柏林2 胡浩然2.辅助隧道封闭后隧道内瓦斯运移富集规律研究[J]. 现代隧道技术, 2025,62(2): 201-211
Copyright 2010 by 现代隧道技术