长大山岭铁路隧道群无砟轨道施工组织的研究

Study of the Construction Organization of Non-Ballasted Track in Long Mountain Railway Tunnel Groups

  • 摘要: 文章借鉴国内外隧道无砟轨道施工经验和相关技术资料,以贵广铁路隧道群双块式无砟轨道项目的工程实践为背景,对山岭地区隧道群无砟轨道施工工装配置和物流组织进行了研究,提出了长大隧道无砟轨道施工采用双线交错和双线分开的作业程序。工程实践表明,采用组合式轨排框架进行现场轨排组装,可以适应曲线半径作业时轨道的调整性能,保证无砟轨道技术指标,具有良好的通用性和快速的施工转换能力;组合式轨道排架精度高、刚度大,可循环使用,从而提高施工工期和节约施工成本。

     

    Abstract: Using domestic and foreign experiences in non-ballasted track construction and related technical documents as references and the double-block non-ballasted track construction of tunnel groups on the Gui-Guang railway as a background, the equipment configuration and organization of logistics for non-ballasted track construction for tunnel groups in mountain areas were studied and the related procedures for construction in a double-track tunnel are proposed in this paper. Engineering practices indicate that in-situ assembly of the track panel using a combined track framework could be adapted to adjust to the curve radius of the track and guarantee the technical indexes of non-ballasted track construction, therefore having rapid construction conversion capability. With high precision and stiffness, the assembled track framework is recyclable to shorten the construction period and save construction costs.

     

/

返回文章
返回