浅覆土大断面小间距矩形顶管施工的环境效应

Environmental Effects Caused by Construction of Rectangular Jacking Pipes with Large Section, Small Space and Shallow Overburden

  • 摘要: 深圳华强北至华新地铁站区间通道工程采用矩形顶管机施工,具有大断面、小间距、浅覆土、上穿地铁隧道、下穿多条地下管线、多条顶管平行施工等特点。文章通过建立数值模型,对注浆压力和机头作用的模拟方法进行了讨论和改进,分析了顶管施工对周边环境的影响。计算结果表明,矩形顶管施工引起的地表沉降槽同样符合Peck公式,土体损失在地层位移的形成中起主导作用;随着多条顶管先后施工,地表沉降槽从V型分布向W型分布转变,地铁隧道竖向位移不断叠加;管棚的支护作用有效减小了地表变形和地下管线变形。

     

    Abstract: A rectangular pipe jacking machine is adopted in construction of the underground passages between North Huaqiang Station and Huaxin Station in Shenzhen, which are characterized by a large section, small spacing,a shallow overburden, parallel construction of several jacking pipes, and passage over a metro tunnel and under underground pipelines. A numerical model is established and the simulation method for the grouting pressure and the function of the pipe jacking machine head is discussed and improved, and the effect of pipe jacking construction on the surrounding environment is analyzed. The results show that: the surface settlement trough caused by rectangular pipe jacking construction complies with the Peck Formula, and ground loss plays a leading role in the formation of stratum displacement; with serial construction of several jacking pipes, the shape of the surface settlement trough changes from a "V" to a "W" and the vertical displacement of the shield tunnel superimposes continuously; and pipe roof support effectively decreases the deformation of ground surface and underground pipelines.

     

/

返回文章
返回