高黎贡山隧道TBM法施工重难点及关键技术分析

Construction Difficulties and Key Techniques for the Gaoligong Mountain TBM Tunnel

  • 摘要: 高黎贡山隧道为目前国内在建最长铁路隧道,其地理位置特殊、地质条件复杂,具有“三高、四活跃”的地质特点。文章全面分析了该隧道采用TBM法施工过程中可能遇到的重难点问题,包括:(1)高达50℃左右的高岩温热害问题;(2)总长为 3 185 m地段的软岩大变形问题;(3)预测最大涌水量为 1.92×105 m3/d的涌水问题;(4)长度达 2 260 m的岩体破碎—极破碎地段 TBM施工问题;(5)Ⅰ级风险隧道的施工安全风险问题;(6)长距离通风问题。在此基础上,对高地温热害防治、软岩大变形控制、涌水应对、TBM过断层破碎带等不良地质段施工关键技术进行了研究与论述,可为后期TBM施工提供技术支撑。

     

    Abstract: The Gaoligong mountain tunnel, characterized by its special geographic location and complicated geologi? cal conditions, is the longest railway tunnel under construction in China. The key points and difficulties that might be encountered during TBM tunnel construction are analyzed, including a high temperature of around 50℃, large deformation of the soft rock with a length of 3,185 m, an estimated maximum water inflow of 1.92 × 105 m3/d, a long seriously fractured section with 2,260 m in length, construction risk management for a tunnel of risk grade I and longdistance ventilation control. Key construction techniques are studied, such as high ground temperature prevention,controlling large deformation for soft rock, water inflow treatment and TBM construction in an unfavorable geological section of a fault fracture zone.

     

/

返回文章
返回