Research on the Dynamic Construction Technology of Slurry Shields Based on the Change of Geological Conditions
(1. CCCC Tunnel Engineerings Co., Ltd., Beijing 100102; 2. CCCC First Highway Engineerings Group Co., Ltd., Beijing 100024)
Download: PDF (4011KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract As the geological conditions in shield tunnelling are becoming increasingly complex, the current practice of determining the appropriate tunnelling parameters through "trial advancing" to guide the subsequent construction can no longer meet the requirements of shield tunnelling that passes through complex geological conditions in long distances. In view of this, this paper puts forward the concept of dynamic construction technology of the slurry shield based on the analysis of geological condition changes through the characteristics of mucks excavated by slurry shields. Based on the construction example of the slurry shield tunnel of Beijing South-to-North Water Diversion Project, which passes through sandy pebble strata with interlayered clay, the performance status and faced issues during shield construction are determined from five aspects, including geological analysis, geotechnical analysis,shield tunnelling parameters analysis, other factor analysis and comprehensive analysis. By this technical concept and method it can realize the real-time and professional control of the whole shield construction process to a certain extent, which is of great significance to ensure the safety and efficiency of shield construction.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
LIU Hongzhi1
2 GAN Congyu1
2 ZHAO Liang1
2 ZUO Shirong1
2 ZHANG Hanshuo1
2
KeywordsSlurry shield   Dynamic construction   Geological analysis   Geotechnical analysis   Tunnelling parameters     
Abstract: As the geological conditions in shield tunnelling are becoming increasingly complex, the current practice of determining the appropriate tunnelling parameters through "trial advancing" to guide the subsequent construction can no longer meet the requirements of shield tunnelling that passes through complex geological conditions in long distances. In view of this, this paper puts forward the concept of dynamic construction technology of the slurry shield based on the analysis of geological condition changes through the characteristics of mucks excavated by slurry shields. Based on the construction example of the slurry shield tunnel of Beijing South-to-North Water Diversion Project, which passes through sandy pebble strata with interlayered clay, the performance status and faced issues during shield construction are determined from five aspects, including geological analysis, geotechnical analysis,shield tunnelling parameters analysis, other factor analysis and comprehensive analysis. By this technical concept and method it can realize the real-time and professional control of the whole shield construction process to a certain extent, which is of great significance to ensure the safety and efficiency of shield construction.
KeywordsSlurry shield,   Dynamic construction,   Geological analysis,   Geotechnical analysis,   Tunnelling parameters     
Cite this article:   
LIU Hongzhi1, 2 GAN Congyu1, 2 ZHAO Liang1 etc .Research on the Dynamic Construction Technology of Slurry Shields Based on the Change of Geological Conditions[J]  MODERN TUNNELLING TECHNOLOGY, 2022,V59(3): 246-252
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2022/V59/I3/246
 
No references of article
[1] ZHANG Bangchao1 LIU Hongliang2 LEI Fengguo2 PENG Guanghuo2.On Settlement Control in Large-diameter EPB Shield Tunnelling under Civil Housing Complex in Upper-soft and Lower-hard Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2022,59(2): 172-181
[2] LIU Laicang1,2 XIA Pengju3 LV Huanjie1,2 WANG Yunzhi1,2 LI Pengfei1,2 MIN Fanlu1,2.Experimental Study on the Property Change of CMC-Modified Seawater Slurry and Filter Cake Formation in Sand Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2022,59(1): 249-255
[3] SONG Yang1 WANG Weiyi2 DU Chunsheng3.On Parameter Optimization for a Slurry Shield Approaching Construction under Existing Subway Tunnels in Water-Rich Pebble and Mudstone Composite Stratum[J]. MODERN TUNNELLING TECHNOLOGY, 2021,58(5): 85-95
[4] YANG Jihua1 GUO Weixin1 YAN Changbin2 MIAO Dong1.Study on Optimization of TBM Driving Parameters Based on the Energy Consumption[J]. MODERN TUNNELLING TECHNOLOGY, 2021,58(1): 54-60
[5] GONG Chenjie1 YANG Junsheng1 FU Jinyang1, 2.Characteristics and Influencing Factors of Segment Cracking of LargeDiameter River-Crossing Shield Tunnelling in Composite Rock Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(5): 30-42
[6] LI Gang1 LI Xiaojun1 YANG Wenxiang2 HAN Dong1.Research on Prediction of TBM Driving Parameters Based on Deep Learning[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(5): 154-159
[7] SHEN Xiang1 YUAN Dajun2 WU Jun3 FU Yanbin1.Analysis and Prediction of Driving Parameters of Shield Tunnelling in Complex Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(5): 160-166
[8] LU Andian1 XIAO Hui2 SHEN Xiang2 FU Yanbin2.Design and Construction Technology of Slurry Shield Used in Shiziyang Water Conveyance Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(5): 226-231
[9] YAN Changbin JIANG Xiaodi.Prediction Model of TBM Net Advance Rate Based on Parameters of Rock Mass and Tunnelling[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(2): 26-33
[10] ZHANG Longguan1 DUAN Wenjun1 ZHUANG Yuanshun1 ZHANG Zhonghua1 LIU Suimei1 ZHANG Feng2.Research of Shield Big Data Preprocessing[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(2): 34-41
[11] LI Qiang1 GAN Penglu2.On Cutter Wearing Control Technology of the Shield Passing through Mixed Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 168-174
[12] ZHANG Mingju1 ZHANG Zhenbo1 CHEN Feng2.Construction Techniques for the Small-radius Curved Shield Tunnels in Water-rich Fractured Stratum with High Pressure[J]. MODERN TUNNELLING TECHNOLOGY, 2018,55(6): 197-203
[13] .[J]. MODERN TUNNELLING TECHNOLOGY, 2018,55(5): 245-253
[14] .Analysis of the Circulation System of a Slurry Shield and the Muck Carrying Ability of a Dredging Pipe[J]. MODERN TUNNELLING TECHNOLOGY, 2018,55(3): 205-213
[15] WANG Zhufeng1,2 FENG Huanhuan1,2.Clay Cake Prevention for a Slurry Shield Cutterhead in Argillaceous Siltstone Stratum[J]. MODERN TUNNELLING TECHNOLOGY, 2017,54(6): 217-222
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY