Construction Scheme and Application Analysis of Synchronous Construction of Subway Shield Tunnels and Freezing Reinforcement for Cross Passages
(Beijing Uni.-Construction Group Co., Ltd.,Beijing 100000)
Download: PDF (7859KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract Taking the east extension project of Beijing Metro Line 7 as a project case, in order to ensure the sched? ule of the opening and operation of the line, the mechanical and electrical installation and decoration of stations,construction of shield tunnels and freezing for cross passages had to be carried out simultaneously. Based on this,during construction, the construction schedule, site conditions (ground surface and interior of stations and tunnels),freezing effect and cost were comprehensively considered, the construction technical scheme that two cross passages share one freezing station was proposed, that is, the freezing station was located in the middle of two cross passages of the tunnel that has achieved breakthrough. By means of optimizing the selection of freezing station units, layout of freezing pipeline, tunnel segment pre-reinforcement support system and other technical measures, synchronous construction of shield tunnels and freezing reinforcement was achieved. According to monitoring and data analysis of the construction process, the development law of the freezing wall and the conditions for the safe excavation of the passages were summarized, and countermeasures for the problems were proposed, such as rise of the cooling water temperature on the site and the ambient temperature. The results show that the construction scheme and relevant technical measures are safe, effective and feasible.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
CHEN Jingang GUO Qiang ZHOU Hailong HUAI Wenbao DONG Xiaoqi
KeywordsSubway tunnels   Shield tunnelling   Cross passages   Freezing method   Scheme optimization   Monitoring and analysis     
Abstract: Taking the east extension project of Beijing Metro Line 7 as a project case, in order to ensure the sched? ule of the opening and operation of the line, the mechanical and electrical installation and decoration of stations,construction of shield tunnels and freezing for cross passages had to be carried out simultaneously. Based on this,during construction, the construction schedule, site conditions (ground surface and interior of stations and tunnels),freezing effect and cost were comprehensively considered, the construction technical scheme that two cross passages share one freezing station was proposed, that is, the freezing station was located in the middle of two cross passages of the tunnel that has achieved breakthrough. By means of optimizing the selection of freezing station units, layout of freezing pipeline, tunnel segment pre-reinforcement support system and other technical measures, synchronous construction of shield tunnels and freezing reinforcement was achieved. According to monitoring and data analysis of the construction process, the development law of the freezing wall and the conditions for the safe excavation of the passages were summarized, and countermeasures for the problems were proposed, such as rise of the cooling water temperature on the site and the ambient temperature. The results show that the construction scheme and relevant technical measures are safe, effective and feasible.
KeywordsSubway tunnels,   Shield tunnelling,   Cross passages,   Freezing method,   Scheme optimization,   Monitoring and analysis     
Cite this article:   
CHEN Jingang GUO Qiang ZHOU Hailong HUAI Wenbao DONG Xiaoqi .Construction Scheme and Application Analysis of Synchronous Construction of Subway Shield Tunnels and Freezing Reinforcement for Cross Passages[J]  MODERN TUNNELLING TECHNOLOGY, 2023,V60(1): 233-240
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2023/V60/I1/233
 
No references of article
[1] GUO Yongjun1 LI Chao2 ZHENG Jianguo3 YU Yongtang4 ZHU Caihui5.Influence of Ground Surcharge on Existing Shield Tunnel Segments in Xi′an Loess Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 61-72
[2] WANG Yonggang1 CUI Yikun1 WU Jiuqi2, 3 HUANG Jun4 SHEN Xiang2, 3 YANG Kui4 SU Dong2, 3.Comparative Analysis of Disc Cutter Forces and Wear under Different Wear Modes[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 73-81
[3] ZHOU Yili1 FENG Kun1 GUO Wenqi1 ZHANG Liangliang2 LI Chunlin3.Study on the Bending Behavior and Damage Characteristics of Longitudinal Segment Joints in Super-large Diameter Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 163-173
[4] YI Dan1 XUE Haoyun2 YANG Shaoyi2 YU Bo1 FENG Kun2 LIN Gang1.Analysis of the Influence of Bolt Failure of Shield Tunnel Segment Structure on Transverse Seismic Response[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 174-181
[5] JIA Yonggang1 HAO Zihan1 LU Weidong1 WU Fan1 YANG Weiwei2.Mechanical Behavior of Steel Fiber Reinforced Concrete Segments with Different Joint Configurations[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 182-196
[6] TAN Xinyu1 WEI Meng1,2 LAN Lingshen1 SHANG Qiang1 ZHANG Haitao1.Experimental Test and Mechanism Study on Soil Adhesion Reduction Techniques for Mud Cake Formation on Shield Cutterheads[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 219-229
[7] LIU Pengfei1,2 ZENG Dexing2 WANG Xiao3 YANG Zhao2 LI Yu2.Experimental Evaluation and Application Study on the Shield Muck Cake Decomposition Agents[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 230-237
[8] CHEN Ming1 ZHAO Dapeng2 ZHANG Jingxiang1 GAO Hui1 WANG Xing1 HAO Jianshuai3 FANG Kuizhen3.The Reuse and Performance Testing of Shield Tunnel Mucks in Synchronous Grouting Materials[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 248-258
[9] ZHANG Ming1, 2, 3 HOU Hao4 CHEN Changqing2, 3 HAN Zhihao5, 6, 7 CHEN Foci2, 3 HE Junpei5.Experimental Study on the Road Performance of Geopolymer-based Solidifiable Fluid Shield Waste Slurry[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 238-247
[10] ZHANG Xiaolong.Mechanical Response Analysis of Subway Shield Tunnel Structure under Pile Foundation Load[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(4): 82-89
[11] LUO Zhenhan1 LIAO Shaoming1 ZHAO shuai.Hybrid Prediction Model for Shield Machine Attitude Based on TPE-XGBoost-GRU and Its Application[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 88-99
[12] HU Yunjin1,2,3 ZHU Mingwei GAO Huicai REN Zhihao1,2,3.null[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 50-59
[13] ZHENG Tengyue1 WANG Shuying1,2 YUAN Xiao1.Optimization of Construction Parameters for Shield Tunnels Undercrossing Existing Lines Based on Numerical Simulation and Machine Learning[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 100-107
[14] LI Hanyuan1,2 FENG Jin1 GUO Hongyu1 XIE Xiongyao2 ZHOU Hongsheng1 SUN Fei.Study on the Combined Bearing Mechanical Characteristics of the Double-layer Lining Structure of Subsea Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 126-138
[15] SU Heng1 WANG Shimin1 ZHU Xuhong2 QIN Shanliang3.Study on the Mechanical Characteristics of Shield Cutter Cutting Pile Foundation Main Reinforcement Considering Spatial Effects[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 139-150
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY