Comparison and Selection of Construction Schemes for the Boom-type Roadheader in Small-section Tunnels
(1. China Railway Development and Investment Group Co., Ltd., Kunming 650000; 2. China Railway Engineering Equipment Group Tunnel Equipment Manufacturing Co., Ltd., Xinxiang 453000)
Download: PDF (4398KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract In order to solve the problems caused by the limited operation space inside the small-section tunnel due to the influence of section size in actual construction, such as multiple process intersections, large mutual interference,periodic cycling of drilling and mucking on the same working face, and the inability to use efficient large-scale mechanical equipment in construction, this paper first puts forward three mechanized construction schemes based on the Longshushan Small-section Tunnel Project in Honghe section of the water diversion project in Central Yunnan,compares and analyzes the construction machinery, construction methods, construction progress and other aspects used in each scheme, and determines the final construction supporting scheme, in which the CTR300S boom-type roadheader, developed by China Railway Engineering Equipment Group Co., Ltd. specially for small-section hydraulic tunnels, is used combined with manual supporting operation. A technical application experimental study was conducted on the selected construction supporting plan after theoretical analysis. The results showed that: (1) the stability of Grade Ⅳ~Ⅴ surrounding rocks is poor, mainly composed of slate, fine sandstone and limestone lithology. Under rich groundwater test cases, the working efficiency of CTR300S boom-type roadheader can reach 20~40 m3/h, and the estimated monthly excavation advance rate can exceed 150 m, achieving the expected progress effect; (2)it is feasible to provide a working platform for installation of arches, shotcrete and other processes at the cutting part of the roadheader for full-section excavation of small-section tunnels.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
LIU Wanlin1 SHANG Mingming2 WANG Quansheng2 WANG Donghong2 WEN Shiyu1
KeywordsWater diversion project in Central Yunnan   Small section   Boom-type roadheader   Mechanical excava? tion   Experimental study     
Abstract: In order to solve the problems caused by the limited operation space inside the small-section tunnel due to the influence of section size in actual construction, such as multiple process intersections, large mutual interference,periodic cycling of drilling and mucking on the same working face, and the inability to use efficient large-scale mechanical equipment in construction, this paper first puts forward three mechanized construction schemes based on the Longshushan Small-section Tunnel Project in Honghe section of the water diversion project in Central Yunnan,compares and analyzes the construction machinery, construction methods, construction progress and other aspects used in each scheme, and determines the final construction supporting scheme, in which the CTR300S boom-type roadheader, developed by China Railway Engineering Equipment Group Co., Ltd. specially for small-section hydraulic tunnels, is used combined with manual supporting operation. A technical application experimental study was conducted on the selected construction supporting plan after theoretical analysis. The results showed that: (1) the stability of Grade Ⅳ~Ⅴ surrounding rocks is poor, mainly composed of slate, fine sandstone and limestone lithology. Under rich groundwater test cases, the working efficiency of CTR300S boom-type roadheader can reach 20~40 m3/h, and the estimated monthly excavation advance rate can exceed 150 m, achieving the expected progress effect; (2)it is feasible to provide a working platform for installation of arches, shotcrete and other processes at the cutting part of the roadheader for full-section excavation of small-section tunnels.
KeywordsWater diversion project in Central Yunnan,   Small section,   Boom-type roadheader,   Mechanical excava? tion,   Experimental study     
Cite this article:   
LIU Wanlin1 SHANG Mingming2 WANG Quansheng2 WANG Donghong2 WEN Shiyu1 .Comparison and Selection of Construction Schemes for the Boom-type Roadheader in Small-section Tunnels[J]  MODERN TUNNELLING TECHNOLOGY, 2023,V60(3): 266-273
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2023/V60/I3/266
 
No references of article
[1] JIANG Yajun1 YU Liangmin1 WANG Cuijuan2 WANG Yongchao2 WANG Huqun.Study on the Performance of Paper Fiber Based Modified Permeable Mortars in Tunnelling[J]. MODERN TUNNELLING TECHNOLOGY, 2022,59(2): 141-149
[2] YUAN Wei1 LU Junfu2 LIU Jinsong1 WU Junmeng1.Cause Analysis of Persistent Heaving of Tunnel Floors in Red-bed Mudstone with Complex Geo-stress[J]. MODERN TUNNELLING TECHNOLOGY, 2022,59(2): 242-250
[3] CHEN Guizhou1,2 CHEN Zheng1,2 JU Guoquan3 WANG Huiwu3 GUO Chun1,2.Study on Relationship between Labor Intensity and Oxygen Concentration in High-altitude Tunnel Construction[J]. MODERN TUNNELLING TECHNOLOGY, 2022,59(1): 118-123
[4] WANG Weiqiang LUO Yonghuan KONG Lingjun ZHANG Yinxi CHEN Yanbei.Numerical Simulation and Experimental Study of Mechanical Properties of GINA Waterstop[J]. MODERN TUNNELLING TECHNOLOGY, 2021,58(5): 237-243
[5] HUANG Jifu XIAO Gongyi.Study on Practical Application and Adaptability of the Roadheader in Transportation Tunnelling[J]. MODERN TUNNELLING TECHNOLOGY, 2021,58(2): 51-62
[6] HU Jianzhong1 WANG Yong2 XU Guoping2 XU Yu2 YU Guangzhong3 GONG Yi2.Experimental Study and Selection Design of Domestic GINA Gasket for the Immersed Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(4): 171-177
[7] ZHEN Zuolin1,3 ZHU Jianghong1 YU Gui3 GAI Yuxi1 ZHANG Huyuan1,4.Thermal Physical Parameters Test on the Surrounding Rocks of Lanzhou Underground Rail Transit[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(2): 163-168
[8] LIN Hong1 WAN Maosen2.Application of Complete Set Mechanized Operation Line of Boom Roadheader in Construction of Railway Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2019,56(2): 188-193
[9] QI Tai-Yue, LI Bin.Application of Boom-type Roadheader in a Metro Tunnel with Complex Cross-sections[J]. MODERN TUNNELLING TECHNOLOGY, 2011,48(4): 32-38
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY