跃龙门隧道软岩大变形两台阶快速成环法施工技术研究

Study on Two-bench Construction Method with Rapid Ring Closure under the Condition of Large Soft Rock Deformation in Yuelongmen Tunnel

  • 摘要: 针对新建成兰铁路跃龙门隧道高地应力软岩大变形施工,提出“主动控制”的理念,结合机械化快速施工的优势,采取“优化轮廓、双层支护、分步预留、锚撑结合、围岩加固、快速封闭”的控制措施,强调对变形发展的过程控制,总结研究形成“两台阶带隧底(短台阶)快速封闭成环施工”关键技术,最终实现了软岩大变形的有效控制,该技术的应用可为同类型软岩大变形隧道工程施工提供借鉴。

     

    Abstract: Given the large deformation of soft rock with high ground stress in the Yuelongmen Tunnel on the newly built Chengdu-Lanzhou Railway, the concept of "active control" has been proposed. In addition to the advantage of rapid mechanized construction, the control measures including "optimized contour, two-layer support, step-by-step reservation, anchor-support combination, surrounding rock consolidation and rapid closure" are employed, where emphasis is put on the process control of deformation development. The key technology of "two-bench (inclusive of tunnel bottom) construction with short bench rapid ring closure" has been developed, to eventually achieve effective control of large deformation in soft rock.

     

/

返回文章
返回