三孔顶管上穿施工对既有隧道与地表变形影响分析

Analysis of the Impact of the Three Pipe Jacking Over-crossing Construction on Existing Tunnel and Surface Deformation

  • 摘要: 依托南昌市新建综合管廊三孔顶管上穿既有地铁隧道工程,通过建立三维数值模型,研究先中间后两边、先两边后中间、从右至左、三孔同时施工4种施工顺序对既有隧道与地表变形影响的差异,比选出最优施工顺序。并进一步探究不同注浆压力、掌子面压力和抗浮配重对既有隧道与地表变形的影响。最终通过现场监测,验证模拟结果的正确性,揭示既有隧道位移与地表变形规律。结果表明:先两边后中间施工顺序最优,其引起的地表沉降、既有隧道竖向位移与水平位移最小,较最大值分别减小18.2%、30.7%、23.8%;增大注浆压力能抑制地表沉降与既有隧道位移的发展,增大掌子面压力能减小地表沉降,但会使既有隧道位移增大,注浆压力与竖向土压力的比值宜控制在2.5~3.8之间,掌子面压力与侧向土压力的比值宜控制在1.88~2.5之间;施加抗浮配重能抑制既有隧道位移,且使隧道拱顶上浮达到最大值后出现回落,配重比为0.5、1.0时的降幅分别为17%和30%;顶管先后施工,地表沉降、沉降槽宽度与既有隧道位移均不断增大,由于阻隔效应,地铁下行线的位移小于上行线位移;监测得到地表最大沉降为13.5 mm,既有隧道拱顶最大竖向位移、道床最大竖向位移、拱腰最大水平位移分别为1.5 mm、1.1 mm、0.8 mm,均在安全范围内。

     

    Abstract: Based on the new three pipe jacking utility tunnel crossing over existing metro tunnel in Nanchang City, a three-dimensional numerical model was established to study the deformation of the existing tunnel and ground surface under four construction sequences: first the middle, then both sides; first both sides, then the middle; right to left; and simultaneous construction of the three pipe jacking. The optimal construction sequence was selected by comparing the impact of these construction sequences on the deformation of the existing tunnel and the ground surface. The study further investigates the effect of different grouting pressures, face pressures, and anti-floating counterweights on the deformation of the existing tunnel and the ground surface. Finally, field monitoring was conducted to verify the accuracy of the simulation results and reveal the displacement and deformation patterns of the existing tunnel and the ground surface. The results show that: (1) The two-sides-first construction sequence is the optimal one, resulting in the least surface settlement, vertical tunnel displacement, and horizontal tunnel displacement, reducing them by 18.2%, 30.7%, and 23.8%, respectively, compared to the maximum values; (2) Increasing grouting pressure can suppress the development of surface settlement and tunnel displacement. Increasing face pressure can re? duce surface settlement but will increase tunnel displacement. The ratio of grouting pressure to vertical soil pressure should be controlled between 2.5 and 3.8, and the ratio of working face pressure to lateral soil pressure should be controlled between 1.88 and 2.5; (3) Applying anti-floating counterweights can suppress tunnel displacement, causing the floating of the tunnel vault to rise to a maximum value before decreasing. The reduction in displacement for counter weight ratios of 0.5 and 1 is 17% and 30%, respectively; (4) During the successive pipe jacking process, the surface settlement, settlement trough width, and tunnel displacement increase with each construction step. Due to the isolation effect, the displacement of the metro's downward line is smaller than that of the upward line; (5) Field monitoring showed a maximum surface settlement of 13.5 mm, with the maximum vertical displacement at the tunnel vault, the maximum vertical displacement at the track bed, and the maximum horizontal displacement at the tunnel waist being 1.5 mm, 1.1 mm, and 0.8 mm, respectively, all within safe limits.

     

/

返回文章
返回