基岩完整隧道衬砌环向裂缝成因分析及其防治措施
Cause Analysis of and Preventive Measures for Circumferential Cracks Occurring in the Lining of a Tunnel with Intact Bedrock
-
摘要: 文章通过向莆铁路线七座完整基岩隧道二次衬砌环向裂缝的统计,对隧道衬砌开裂的原因进行了综合分析,阐述了混凝土结构裂缝的危害大小程度,以及设计及施工管理过程中对衬砌裂缝的控制途径,并对此提出了相应的处理措施和建议。Abstract: Based on the statistics of the circumferential cracks in the secondary linings of the seven tunnels with intact bedrocks on the Xiangtang-Putian railway, a comprehensive analysis of the causes of lining cracking was performed. This paper elaborates on the troubles encountered and the control methods used during the design and construction phases in light of the cracks that occurred in the concrete structures. In addition, corresponding countermeasures and suggestions are addressed.