悬臂掘进机成套机械化作业线在铁路隧道施工中的应用

Application of Complete Set Mechanized Operation Line of Boom Roadheader in Construction of Railway Tunnels

  • 摘要: 新磨溪二号隧道为Ⅳ级、Ⅴ级软弱围岩隧道,穿越岩溶、滑坡等不良地质及石膏等特殊岩土,地质条件复杂,施工风险高;而且该隧道邻近既有营业线,施工难度大,安全要求高,采用传统爆破法施工难以满足进度与安全要求。文章对比分析了悬臂掘进机法相较于传统钻爆法的施工优势,阐述了悬臂掘进机成套机械化作业线设备配套技术及施工组织方案。实际应用效果表明,悬臂掘进机成套机械化作业线作为一种较为先进的隧道非钻爆法施工方法,在隧道工程施工中具有广阔的应用前景。

     

    Abstract: The surrounding rocks of the new Moxi No. 2 tunnel, passing through adverse Karst, landslide and gymsum strata, are of grade Ⅳ and Ⅴ soft rock, the geological condition is complex and construction risks are high.Moreover this new tunnel is adjacent to an existing operating railway line and the construction is more difficult and requirement of safety is high, it is hard to meet the requirements of schedule and safety with traditional drill and blast method. Compared with the conventional drill and blast method, the advantages of boom roaheader were analyzed, the matching equipment techniques and construction organization scheme of complete set mechanized operation line of boom roadheader were described. The practice shows that the application prospect of complete set mechanized operation line of boom roadheader used in tunnel construction is bright as an advanced non-drill and blast construction method.

     

/

返回文章
返回