富水复杂地层中长距离大坡度煤矿斜井TBM选型
中国铁建大桥工程局集团有限公司
TBM Selection for a Long-Distance Inclined Coal Mine Shaft with a Large Gradient in Water-Rich Stratum
China Railway Construction Bridge Engineering Group Co., Ltd
Download: PDF (954KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 文章以某矿井主斜井采用TBM施工为背景,分析指出了该工程所面临的主要问题和技术挑战,并对各类型盾构和TBM在该工程中的适应性进行了理论对比分析,提出了煤矿长距离斜井施工采用双模式TBM的设备机型。鉴于煤矿斜井TBM施工面临的长距离、大坡度、大埋深、有毒有害气体危害、富水复杂地层及施工进度要求高等问题,文章对双模式TBM的主要功能设计及设备的选型配置进行了研究,提出了双模式TBM应对不同技术问题的设计方案和设备配置技术措施。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
关键词煤矿斜井     双模式TBM     富水复杂地层     TBM选型     
Abstract: The main problems and challenges of TBM construction for an inclined shaft of a coal mine were analyzed, and the adaptability of various kinds of TBMs were compared. Ultimately, a dual-mode TBM was suggested for the long distance inclined shaft of a coal mine shaft with a large gradient in a water-rich stratum. Considering the specific characteristics of a long distance, a large gradient, a great overburden, presence of toxic gas, and a complex stratum with abundant water and strict construction progress, the main function, selection and configuration of the dual-mode TBM are studied, and the suggested design scheme and equipment configuration are presented.
KeywordsInclined shaft of coal mine  ,   Dual-mode TBM  ,   Complex Stratum with abundant water  ,   TBM selection     
基金资助:

1 国家科技支撑计划资助项目(2013BAB10B01)

2 天津市滨海新区科技创新项目(2012-BK120034)

作者简介: 李铁成(1979-),男,高级工程师,主要从事城市地铁盾构施工及斜井TBM(盾构)施工技术工作, E-mail: 35151756@qq.com
引用本文:   
.富水复杂地层中长距离大坡度煤矿斜井TBM选型[J]  现代隧道技术, 2015,V52(2): 174-179
.TBM Selection for a Long-Distance Inclined Coal Mine Shaft with a Large Gradient in Water-Rich Stratum[J]  MODERN TUNNELLING TECHNOLOGY, 2015,V52(2): 174-179
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2015/V52/I2/174
 
没有本文参考文献
Copyright 2010 by 现代隧道技术