Application of Blasting Techniques with the Reserved Smooth Blasting Layer in Full-face Construction of Large and Long Tunnels
(1 School of Source and Safety Engineering, Central South University, Changsha 410083; 2 Advanced Research Center, Central South University, Changsha 410083; 3 CCCC First Highway Fifth Engineering Co., Ltd., Beijing 100024)
Download: PDF (3197KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract As for the traditional smooth blasting of the large cross–section tunnel, it is hard to ensure that all pe? ripheral holes detonate simultaneously and there are a series of problems like low contour flatness and residual blasthole trace rate, large overbreak and underbreak, poor shaping quality and so on. Based on the East Tianshan tunnel,the blasting technique with the reserved smooth blasting layer is adopted to conduct full-face construction, and good smooth blasting effect is obtained by optimizing initiation sequence, network and parameters. The site test results show that the average linear overbreak is controlled within 15-25 cm which is reduced by 80% compared with traditional smooth blasting; the concrete consumption of primary support is reduced by 2.63 m3/m; and the parameters of practical cyclical advance rate, residual blasthole trace rate, unit explosive consumption and so on are significantly improved.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
MA Chunde1
2 LIU Zelin1 ZHENG Jing3 LONG Shan1 ZHANG Jianqiu3 GUO Chunzhi1
KeywordsLarge cross-section tunnel   Full-face construction   Blasting technique with reserved smooth blasting layer     
Abstract: As for the traditional smooth blasting of the large cross–section tunnel, it is hard to ensure that all pe? ripheral holes detonate simultaneously and there are a series of problems like low contour flatness and residual blasthole trace rate, large overbreak and underbreak, poor shaping quality and so on. Based on the East Tianshan tunnel,the blasting technique with the reserved smooth blasting layer is adopted to conduct full-face construction, and good smooth blasting effect is obtained by optimizing initiation sequence, network and parameters. The site test results show that the average linear overbreak is controlled within 15-25 cm which is reduced by 80% compared with traditional smooth blasting; the concrete consumption of primary support is reduced by 2.63 m3/m; and the parameters of practical cyclical advance rate, residual blasthole trace rate, unit explosive consumption and so on are significantly improved.
KeywordsLarge cross-section tunnel,   Full-face construction,   Blasting technique with reserved smooth blasting layer     
Cite this article:   
MA Chunde1, 2 LIU Zelin1 ZHENG Jing3 LONG Shan1 ZHANG Jianqiu3 GUO Chunzhi1 .Application of Blasting Techniques with the Reserved Smooth Blasting Layer in Full-face Construction of Large and Long Tunnels[J]  MODERN TUNNELLING TECHNOLOGY, 2019,V56(6): 173-180
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2019/V56/I6/173
 
No references of article
[1] WANG Mingnian1,2 GUO Xiaohan1,2 CUI Peng1,2 YU Li1,2.Discussion on the Key Techniques for Disaster Prevention, Evacuation and Rescue of Large-scale Railway Tunnel Group in High Altitude Area[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 1-7
[2] ZHU Yongsheng1 LI Pengfei2.Research Progress of Hoek-Brown Strength Criterion and Determination of Mechanical Parameters of Rock Mass[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 8-17
[3] ZHENG Yuchao1 ZHANG Wensheng1 SUN Keguo1 CAI Jialiang1 LI Jie2 LENG Biao1 ZHAO Ruiwen2.Study on the Stability of Large-Span Tunnel by Distinct Element Based Strength Reduction Method[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 18-25
[4] LIU Xuezeng1,2 CAI Xin3 DING Maorui3 CHEN Fubin3 DENG Feng3.Study on Health Evaluation Method of Large-Span Highway Tunnel with Fractured Surrounding Rocks[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 26-35
[5] TAO Weiming1 LI Huayun2 ZHANG Zhiqiang2 GUO Yongfa3.Study on the Shear Strength of Surrounding Rocks and Mechanical Behaviors of Supporting Structure of the Shallow-buried Tunnel in Swelling Soil[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 36-43
[6] MA Shiqiang1,2.On Relationship between Surrounding Rock Deformation and Surrounding Rock Pressure under Large Deformation of Soft Rock[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 44-50
[7] DU Jun1,2 MEI Zhirong2 FU Lilei3 CHEN Yongzhao3.Study on Working Face Stability of the Shallow-buried Tunnel in Soft Surrounding Rocks Based on Strength Reduction Theory[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 51-57
[8] GUO Chenggang1 GUO Yongfa2 ZHU Menglong3 ZHANG Qingwen3.Hydrogeological Investigation of the Underground River of Karst Tunnel in Carbonate Rock of Red Bed[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 58-64
[9] ZHAN Xianjun PEI Taotao ZHOU Jibing.Visualization Analysis of Metro Station Deformation Based on Thermodynamic Diagram[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 65-69
[10] CAI Yaning1 HUANG Qingjie2.Relevant Standards and Quality Management of the Mould for Reinforced Concrete Segments of Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 70-75
[11] YAN Tao1 LI Kunjie1 QIN Pengcheng1 CHEN Jingyu1,2 LIN Rui3 ZUO Qiang3.Calculation Method for the Surrounding Rock Pressure of Mined Lower Tunnel Structure of a Metro Station Built by Combination of Open Cut and Mined Method[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 76-82
[12] WANG Jun LIN Guojin.Study on the Characteristics of Secondary Lining Cracking under the Effect of Rheological Load[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 83-90
[13] LIN Zhibin ZHANG Boyang YANG Dafang.Simulation Study on Foundation Pit Excavation in Soft Soil Considering Effect of Creep and Seepage[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 91-98
[14] PENG Qi.Influence of Foundation Construction and Additional Load of Transfer Structure on Underneath Metro Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 99-104
[15] PENG Yan1,2 FANG Hui1,2 LV Qinyin1,2.Forward and Inversion Simulation of Tunnel Reflection Wave Tomography and a Contrastive Analysis of TRT Inversion[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(1): 105-114
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY