MODERN TUNNELLING TECHNOLOGY 2024, Vol. 61 Issue (5) :1-9    DOI:
Current Issue | Next Issue | Archive | Adv Search << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
Design and Application of a Prefabricated Loading Platform for Full-scale Shield Tunnel Test
(1. China Academy of Railway Sciences(Shenzhen)Research and Design Institute, Shenzhen 518000; 2. College of Civil and Transportation Engineering, Shenzhen University, Shenzhen 518000; 3. Underground Polis Academy, Shenzhen University,Shenzhen 518000)
Download: PDF (5146KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract Operational shield tunnels are often affected by nearby surface loads, excavation of foundation pits, and piling activities. The external complex loads acting on the shield tunnel can disrupt the original force balance of the structure, potentially leading to excessive deformation or damage. Conducting full-scale tests is the most direct and effective means of studying the mechanical performance and failure characteristics of tunnel structures under complex loads to accurately assess the applicability of tunnel structures. To expand the applicability of full-scale tests for shield tunnels, a prefabricated steel reaction frame suitable for full-scale tests of shield tunnel structures with different sections has been proposed. The horizontal applicability of the reaction frame for different sections and sizes of structural tests is achieved through the combination of different standard units and flange-type node connections. In the vertical direction, nested column connections are adopted to effectively solve the connection and shear transfer between layers of the reaction frame. Meanwhile, the overall stress and node strength of the reaction frame were checked against four extreme loading conditions, and the feasibility of this prefabricated loading platform was further verified through the prototype structure loading test of a circular shield tunnel.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
CHEN Xiangsheng1
2
3 CHEN Weijie2 LI Rongkang2 GU Wentian1 LU Yuan1 LI Qiang2
3 SU Dong2
3
KeywordsShield tunnel   Full-scale test   Prefabricated reaction frame   Flange-type node   Nested column     
Abstract: Operational shield tunnels are often affected by nearby surface loads, excavation of foundation pits, and piling activities. The external complex loads acting on the shield tunnel can disrupt the original force balance of the structure, potentially leading to excessive deformation or damage. Conducting full-scale tests is the most direct and effective means of studying the mechanical performance and failure characteristics of tunnel structures under complex loads to accurately assess the applicability of tunnel structures. To expand the applicability of full-scale tests for shield tunnels, a prefabricated steel reaction frame suitable for full-scale tests of shield tunnel structures with different sections has been proposed. The horizontal applicability of the reaction frame for different sections and sizes of structural tests is achieved through the combination of different standard units and flange-type node connections. In the vertical direction, nested column connections are adopted to effectively solve the connection and shear transfer between layers of the reaction frame. Meanwhile, the overall stress and node strength of the reaction frame were checked against four extreme loading conditions, and the feasibility of this prefabricated loading platform was further verified through the prototype structure loading test of a circular shield tunnel.
KeywordsShield tunnel,   Full-scale test,   Prefabricated reaction frame,   Flange-type node,   Nested column     
Cite this article:   
CHEN Xiangsheng1, 2, 3 CHEN Weijie2 LI Rongkang2 GU Wentian1 LU Yuan1 LI Qiang2 etc .Design and Application of a Prefabricated Loading Platform for Full-scale Shield Tunnel Test[J]  MODERN TUNNELLING TECHNOLOGY, 2024,V61(5): 1-9
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2024/V61/I5/1
 
No references of article
[1] WEI Lixin1 YANG Chunshan1 LIU Liying1 SONG Qilong2,3 SU Dong2,3.Research on the Stability of the Working Face of Large-diameter Shield Tun? nelling in Upper Hard and Lower Soft Composite Strata[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 21-28
[2] QI Jun1 WANG Zhongjie2,3,4 CHEN Zijun1 LIN Cungang2,3,4 XIE Wenjiang1 LIANG Yu2,3,4.Analysis of the Parameter Values for Settlement Trough Width Induced by Shield Tunnel Excavation in Deep Soil[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 29-41
[3] YUAN Zuobo1 JIAN Wenyang2 WANG Duo1 LIANG Yu2 HU Song1 LIN Cungang2 QIN Yingbin1ZHAO Chenyang2.Research on the Mechanism of Ground Deformation Induced by Shield Tunnelling under the Influence of Leakage from Pressurized Water Supply Pipelines[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 174-182
[4] YANG Chunshan1 XU Shiyang2 WEI Lixin1 CHEN Junsheng3.Experimental Study on the Mechanical Characteristics of Shield Tunnels under Vertical Jacking[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 210-218
[5] ZHANG Yu1 ZHOU Lu1 SUN Xiaohe2 LI Jun1 SHI Chenghua2 LIU Shengli.Research on Causes and Countermeasures of Water Leakage in Subway Tunnels in Coastal Area[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 234-424
[6] LIU Bo1,2 ZHENG Jinlei1,3,4 ZHANG Zhao1 MA Jianfei4.Study on Mechanical Model for Longitudinal Deformation of Existing Shield Tunnel Caused by New Tunnel Over-crossing Construction[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 112-118
[7] LIU Xiaohui1 FENG Kun1 GUO Wenqi1 LU Xuanyi1 PENG Changsheng2 LI Jiaoyang2.Study on the Influence of Construction Methods of Internal Structures on Longitudinal Mechanical Characteristics of Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 151-160
[8] ZHU Meiheng1 CHEN Sirui2 HUANG Zhongkai2 LI Yongbo1 ZHANG Wuyu3 ZHANG Dongmei2.Study on the Deformation Law of Large-diameter Fully Prefabricated Assembled Shield Tunnels under Ground Surcharge[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 161-171
[9] WANG Zhiyuan1 YANG Hao2 LIN Gang1 LIAN Zhengzhou2 YU Bo1.Analysis of the Impact of Connecting Bolts on the Vibration Response of Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 172-179
[10] CAI Guangyuan1 TANG Zeren2 CHEN Chen3 ZHU Yuanchang2 YU Pengchen3 LIU Xian2.Research and Development of Intelligent Assembly Equipment for Prefabricated Mid-partition Walls with Large Slenderness Ratios[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 275-282
[11] HUANG Kan WU Qijiang DENG Xi LI Hui.Study on Loose Soil Pressure Calculation of Shield Tunnel Based on Linear Change of the Included Angle of Slip Surface[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(3): 8-17
[12] CHEN Libao1 FENG Kun2 SUN Wenhao1 XING Wenjie2 PAN Jin2 GENG Junyang2 WANG Junling3.Study on Numerical Simulation of Chloride Ion Erosion of Lining Segment Components under the Action of High Hydraulic Pressure[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(3): 131-140
[13] GE Zhaoguo.Study on Impact Zoning Method and Zoning Control Technique for Construction of Large-diameter Shield Tunnel Adjacent to Viaduct Pile Foundation Group[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(3): 276-289
[14] ZHU Weibin1,2,3 MI Jinsheng2,3 WANG Hui2,3,4 ZHONG Changping1,2,3.Innovation and Prospects of Shield Tunnelling Technology in Mixed Ground[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(2): 90-104
[15] CHEN Jian1,2,3,4 YUAN Dajun5 SU Xiuting1,2 WANG Zhikui1,2,3.Progress and Prospects of Construction Technology for Ultra-Large Diameter Underwater Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(2): 124-138
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY