MODERN TUNNELLING TECHNOLOGY 2011, Vol. 48 Issue (4) :110-115    DOI:
Current Issue | Next Issue | Archive | Adv Search << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
Design and Construction of the Zhongwei Yellow River Tunnel of the West-East Gas
(1 South-west Branch of China Petroleum Engineering Design Co., Ltd., Chengdu  610017;
2 Jian'an Company of China Railway 18th Engineering Bureau Group, Gaobeidian  074000)
Download: PDF (0KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract  The Zhongwei Yellow River tunnel, the "throat project" and standby passage of the west-east gas transmission programme as well as main passage of west-east gas transmission line 2, has a maximum capacity for gas transmission of 470×108 m3/year. The engineering geology, hydrogeology, design philosophy, and construction practice of Zhongwei Yellow River tunnel are introduced, and the design and construction characteristics of a submerged tunnel for oil and gas transmission are summarized.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
XIANG Yong-1
YANG Cheng-Gang-1
WU Ke-Xin-1
HAO Wu-Fei-2
Keywords Gas pipe   Underwater tunnel   Structral design   Water explration   Blasting construction     
Abstract:  The Zhongwei Yellow River tunnel, the "throat project" and standby passage of the west-east gas transmission programme as well as main passage of west-east gas transmission line 2, has a maximum capacity for gas transmission of 470×108 m3/year. The engineering geology, hydrogeology, design philosophy, and construction practice of Zhongwei Yellow River tunnel are introduced, and the design and construction characteristics of a submerged tunnel for oil and gas transmission are summarized.
Keywords Gas pipe,   Underwater tunnel,   Structral design,   Water explration,   Blasting construction     
published: 2011-01-21
Cite this article:   
XIANG Yong-1, YANG Cheng-Gang-1, WU Ke-Xin-1 etc .Design and Construction of the Zhongwei Yellow River Tunnel of the West-East Gas[J]  MODERN TUNNELLING TECHNOLOGY, 2011,V48(4): 110-115
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2011/V48/I4/110
 
No references of article
[1] WANG Bo-1, GUO Xin-Xin-1, HE Chuan-1, WU De-Xing-2.[J]. MODERN TUNNELLING TECHNOLOGY, 2018,55(5): 1-10
[2] .Scope Affected by Metro Tunnel Construction Blasting in Qingdao[J]. MODERN TUNNELLING TECHNOLOGY, 2018,55(3): 76-80
[3] ZHANG Wen-Xin.Safety Analysis of an Existing Tunnel Lining Structure during Water Diversion Tunnel Blasting Construction[J]. MODERN TUNNELLING TECHNOLOGY, 2016,53(4): 154-158
[4] Tuo Yongfei, Guo Xiaohong.General Design and Key Technologies of the Nanjing Weisan Road River-Crossing Tunnel Project[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 1-6
[5] Lin Xin1, Shu Heng1, Zhang Yaguo2, Yang Linsong1, Li Jin1, Guo Xiaohong1.Study of the Longitudial Profile Optimization of Large-Diameter Shield Tunnels in Mixed Ground with Very High Water Pressure[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 7-14
[6] Yao Zhanhu1, Yang Zhao2, Tian Yi1, Hu Huitao1.Key Construction Technology for the Nanjing Weisan Road River-Crossing Tunnel Project[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 15-23
[7] Li Xinyu, Zhang Dingli, Fang Qian, Song Haoran.On Water Burst Patterns in Underwater Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 24-31
[8] Shu Heng, Wu Shuyuan, Li Jian, Guo Xiaohong.Health Monitoring Design for Extra-Large Diameter Underwater Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 32-40
[9] Liu Guangfeng1, Chen Fangwei2, Zhou Zhi1, Zhang Shilong3, Liu Mingqiang1.Identification of Investment Risks for River-Crossing Tunnels Based on Grey Fuzzy Multi-Attribute Group Decision Making[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 41-48
[10] Yao Zhanhu.Construction Risk Assessment for the Shield-Driven Section of the Nanjing Weisan Road River-Crossing Project[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 49-54
[11] Zhang Boyang1, Zhao Xiaopeng1, Zhang Yaguo2, Chen Yu1.Risk Control for Saturated Hyperbaric Intervention in Slurry Shield Tunnelling[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(4): 55-61
[12] Li Yufeng1,2, Peng Limin1, Lei Mingfeng1,2.Dynamics Issues Regarding High-Speed Railway Crossing Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(2): 8-15
[13] Zhang Han1,2, Li Yingming1,3, Ren Fangtao2, Yang Mingdong3.Elasto-Plastic Analysis of the Surrounding Rock of a Tunnel/Roadway Based on the Zienkiewicz-Pande Criterion[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(2): 30-35
[14] Zhou Zelin, Chen Shougen, Li Yansong.Study of the Mechanical Characteristics of the Support Structure of a Deeply Buried Diversion Tunnel in Soft Rock[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(2): 36-43
[15] Jin Dalong, Li Xinggao.Model Test of the Relationship between the Face Support Pressure and Ground Surface Deformation of a Shield-Driven Tunnel in Sand Stratum[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(2): 44-51
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY