Studies on the Site Selection of a Segment Prefabrication Factory for the Immersed Tunnel of the Hong Kong-Zhuhai-Macao Bridge Project
1 Dept. of Civil Engineering, South China University of Technology
2 State Key Laboratory of Subtropical Building Science, South China University of Technology
Abstract This paper introduces the selection process for the site of a segment prefabrication factory for the immersed tunnel of the Hong Kong-Zhuhai-Macao Bridge Project (HZM Bridge). The proposed sites for the prefabrication factory were Longxue Island and Guishan Island. This paper explicates the factors used in site selection, including a survey of the prefabrication factory, work flow, and the importance to the HZM Bridge. Based on a comparison of their geographic positions, transportation conditions, and existing problems regarding geology and geotechnical engineering. Guishan Island was chosen as the site of the segment prefabrication factory.
Abstract:
This paper introduces the selection process for the site of a segment prefabrication factory for the immersed tunnel of the Hong Kong-Zhuhai-Macao Bridge Project (HZM Bridge). The proposed sites for the prefabrication factory were Longxue Island and Guishan Island. This paper explicates the factors used in site selection, including a survey of the prefabrication factory, work flow, and the importance to the HZM Bridge. Based on a comparison of their geographic positions, transportation conditions, and existing problems regarding geology and geotechnical engineering. Guishan Island was chosen as the site of the segment prefabrication factory.
Keywords:
published: 2012-03-19
Cite this article:
CHEN Jun-Sheng- 12,
Mo-Hai-Hong-12,
LIU Shu-Zhuo-1 etc
.Studies on the Site Selection of a Segment Prefabrication Factory for the Immersed Tunnel of the Hong Kong-Zhuhai-Macao Bridge Project[J] MODERN TUNNELLING TECHNOLOGY, 2012,V49(6): 122-127