Study on the Mechanical Characteristics of Shield Cutter Cutting Pile Foundation Main Reinforcement Considering Spatial Effects
(1. State Key Laboratory of Intelligent Geotechnics and Tunnelling (Southwest Jiaotong University), Ministry of Education,Chengdu, 610031; 2. PowerChina Southern Investment. Co., Ltd, Shenzhen 518000; 3. PowerChina Sinohydro Bureau 7 Co., Ltd,Chengdu 610213 )
Download: PDF (8162KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract Based on the shield cutting municipal underground pile group in the Guangzhou-Dongguan-Shenzhen In? tercity Rail Transit tunnel project, a mathematical model for shield cutters cutting different spatially distributed pile foundations is established. Numerical simulation methods are used to explore the impact of spatial effects on the shield cutting pile group, and optimization suggestions for tunnelling parameters are proposed and validated based on the engineering practice. The research results show that:(1) The spatial distribution of pile foundations during shield cutting can be characterized by the cutter′s cutting angle. When the cutting angle approaches 90°, the pile foundation is near the center of the cutterhead; when the cutting angle approaches 0°, the pile foundation is near the edge of the cutterhead. (2) When cutting the reinforcement in pile foundations near the edge of the cutterhead, the cutter tools tend to break the reinforcement rather than cut it. As the pile foundation moves from the center of the cutterhead to the edge, the shear force exerted on the reinforcement by the cutters decreases significantly, by up to 56.7%, while the tensile force increases significantly. (3) The closer the pile foundation is to the edge of the cutterhead, the larger the cutting angle left on the reinforcement by the cutting tool, and the longer the cutting. (4) When cutting pile foundations near the edge, the shield machine can appropriately increase the penetration, thrust, and torque, which in turn increases the shear force of the cutters on the reinforcement at the cutterhead edge, facilitating cutting reinforcement.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
SU Heng1 WANG Shimin1 ZHU Xuhong2 QIN Shanliang3
KeywordsShield tunnelling   Numerical simulation   Spatial effects   Mechanical characteristics   Tunnelling parame? ters     
Abstract: Based on the shield cutting municipal underground pile group in the Guangzhou-Dongguan-Shenzhen In? tercity Rail Transit tunnel project, a mathematical model for shield cutters cutting different spatially distributed pile foundations is established. Numerical simulation methods are used to explore the impact of spatial effects on the shield cutting pile group, and optimization suggestions for tunnelling parameters are proposed and validated based on the engineering practice. The research results show that:(1) The spatial distribution of pile foundations during shield cutting can be characterized by the cutter′s cutting angle. When the cutting angle approaches 90°, the pile foundation is near the center of the cutterhead; when the cutting angle approaches 0°, the pile foundation is near the edge of the cutterhead. (2) When cutting the reinforcement in pile foundations near the edge of the cutterhead, the cutter tools tend to break the reinforcement rather than cut it. As the pile foundation moves from the center of the cutterhead to the edge, the shear force exerted on the reinforcement by the cutters decreases significantly, by up to 56.7%, while the tensile force increases significantly. (3) The closer the pile foundation is to the edge of the cutterhead, the larger the cutting angle left on the reinforcement by the cutting tool, and the longer the cutting. (4) When cutting pile foundations near the edge, the shield machine can appropriately increase the penetration, thrust, and torque, which in turn increases the shear force of the cutters on the reinforcement at the cutterhead edge, facilitating cutting reinforcement.
KeywordsShield tunnelling,   Numerical simulation,   Spatial effects,   Mechanical characteristics,   Tunnelling parame? ters     
Cite this article:   
SU Heng1 WANG Shimin1 ZHU Xuhong2 QIN Shanliang3 .Study on the Mechanical Characteristics of Shield Cutter Cutting Pile Foundation Main Reinforcement Considering Spatial Effects[J]  MODERN TUNNELLING TECHNOLOGY, 2025,V62(3): 139-150
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2025/V62/I3/139
 
No references of article
[1] GE Zhenghui ZHENG Jianguo1 LI Xinzhi CHEN Peng3 NING Zhiwei WANG Pengcheng2.Field Measurement and Numerical Study on Deformation Behavior of Initial Supports with Different Arch Types[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 40-49
[2] HU Yunjin1,2,3 ZHU Mingwei GAO Huicai REN Zhihao1,2,3.null[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 50-59
[3] LI Yuhua1 GAO Yawei ZHONG Qiufeng1 QIN Lixuan2 LI Junjie CHENG Zhiming2 HUANG Yonghui.Study on the Blasting Effect of Tunnel Wedge Cut under Different Cut Hole Angles[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 108-116
[4] LI Hanyuan1,2 FENG Jin1 GUO Hongyu1 XIE Xiongyao2 ZHOU Hongsheng1 SUN Fei.Study on the Combined Bearing Mechanical Characteristics of the Double-layer Lining Structure of Subsea Shield Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 126-138
[5] WANG Shuaishuai FU Yifan2,3 XU Yong1 SHI Jingfeng1 GUO Chun2,3.Parametric Study on Air Chamber Ventilation in Tunnelling Using Relay Fans for Airflow Distribution[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 240-248
[6] CHEN Yunyao.Risk Mitigation Measures and Excavation Analysis of Shield Launching beneath an Existing Metro Station on the First Terrace of the Yangtze River[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(3): 249-258
[7] WU Weisong1 LIANG Tianyi2 CAI Zhe2 FANG Yingran3 YAN Tao4 LIU Xiaohai4 LI Xinggao3.Influence of Shield Cutter Layered Configuration and Cutting Parameters on the Fracture Mechanism of Hollow Pipe Piles[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(2): 172-182
[8] LI Jing1 LUO Lusen1 ZHANG Bailin2 HU Haoran2.Study on Gas Migration and Accumulation Patterns in Tunnels after Sealing Auxiliary Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(2): 201-211
[9] GUO Ying PENG Wenqing CHEN Shiqiang ZHANG Qiong WANG Jiawei.Calculation Method and Validation of Equivalent Length for Traffic Tunnel Ventilation Model Test[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(2): 230-240
[10] ZHANG Guang1 GONG Qiuming1 XIE Xingfei1 PEI Chengyuan2 SHANG Ceng2.Interval Prediction of TBM Parameters in Stable Excavation Sections Based on Bootstrap-COA-BiGRU Model[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(2): 121-131
[11] ZHANG Huan1, 2 ZHANG Shishu3 LI Tianbin1, 2 YANG Gang1, 2 LI Shisen1, 2 XIAO Huabo3 CHEN Weidong3.GAPSO-LightGBM-based Intelligent Prediction Method of Surrounding Rock Grade in TBM Tunnelling[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(2): 98-109
[12] HU Zhinan1 MAO Hongtao1 LIU Zhichun1 LIU Zhanliang2 MENG Xiangfei3.Study on the Impact of Foundation Pit Construction on the Deformation of Operating Metro Tunnels and Impact Zoning[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(1): 66-73
[13] YI Zhuangpeng WANG Shen'ao TANG Xinchao CHEN Zhiwei.Study on the Vortex-induced Vibration Characteristics of Multi-lane Wide-section Submerged Floating Tunnels Based on CFD[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(1): 92-102
[14] MU Haixing1 FENG Kun1 GUO Wenqi1 YANG Shaoyi1 ZHANG Liangliang2.Study on the Mechanical Behavior and Failure Characteristics of Ultra-large Diameter Shield Tunnel Segment Structures[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(1): 125-134
[15] MU Zheng LI Fulin.Study on the Effect of Shield Tunnelling Parameters on Cutting Performance of Reinforced Concrete Based on FEM-DEM Coupling Method[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(1): 147-156
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY