Construction Ventilation Scheme for the Huayingshan Extra-Long
Tunnel on the Nanchong-Dazhu-Liangping Expressway
(1  Nanchong-Chongqing Expressway Co. Ltd., Nanchong  637000;
2  Key Laboratory of Transportation Tunnel Engineering, Southwest Jiaotong University, Chengdu  610031)
Download: PDF (0KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract The newly-built Huayingshan tunnel on the Nanchong-Dazhu-Liangping expressway is 8168m long with its entrance and exit passing through coal strata. Because it is a gas-rich tunnel, construction ventilation is a key component of the construction engineering. In this paper, based on current mechanical ventilation modes and the characteristics of the Huayingshan Tunnel, a combination mode of forced ventilation and jet flow gallery ventilation is adopted. By calculating the amount of fresh air required for tunnel ventilation, dividing the work area in light of gas concentration, and calculating the specific resistances of the ventilation ducts and tunnel, the optimal configuration for the construction ventilation fans is carried out, and the construction ventilation scheme for each work area is determined.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
Keywords    Extra-long gas-rich tunnel   Construction ventilation   Equipment configuration     
Abstract: The newly-built Huayingshan tunnel on the Nanchong-Dazhu-Liangping expressway is 8168m long with its entrance and exit passing through coal strata. Because it is a gas-rich tunnel, construction ventilation is a key component of the construction engineering. In this paper, based on current mechanical ventilation modes and the characteristics of the Huayingshan Tunnel, a combination mode of forced ventilation and jet flow gallery ventilation is adopted. By calculating the amount of fresh air required for tunnel ventilation, dividing the work area in light of gas concentration, and calculating the specific resistances of the ventilation ducts and tunnel, the optimal configuration for the construction ventilation fans is carried out, and the construction ventilation scheme for each work area is determined.
Keywords ,   Extra-long gas-rich tunnel,   Construction ventilation,   Equipment configuration     
published: 2012-03-10
Cite this article:   
.Construction Ventilation Scheme for the Huayingshan Extra-Long
Tunnel on the Nanchong-Dazhu-Liangping Expressway[J]  MODERN TUNNELLING TECHNOLOGY, 2013,V50(4): 188-196
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2013/V50/I4/188
 
No references of article
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY