盾构隧道管片接缝渗漏水嵌缝处理试验研究
(1同济大学土木工程学院地下建筑与工程系, 上海 200092;2 同济大学岩土及地下工程教育部重点实验室, 上海200092;3 中交第二公路勘察设计研究院有限公司, 武汉430056)
Experimental Study on Caulking Treatment Against Water Leakage in Shield Tunnel Segment Joints
(1 Department of Geotechnical Engineering, College of Civil Engineering, Tongji University, Shanghai 200092; 2 Key Laboratory of Geotechnical and Underground Engineering of the Ministry of Education, Tongji University, Shanghai 200092; 3 CCCC Second Highway Consultants Co., Ltd., Wuhan 430056)
Download: PDF (2195KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 为了探究盾构隧道管片接缝渗漏水嵌缝处理措施的效果及其适用性,文章依托国内某盾构隧道工程进行管片渗漏水情况排查统计,并制作了混凝土构件试件,利用同济大学自主研发的三向水压加载防水试验系统,对实际工程中采用的渗漏水处理措施——嵌缝密封法进行了多组室内试验研究。结果表明:(1)采用三元乙丙嵌缝密封条处理管片接缝渗漏水,能够满足Ⅰ类渗漏水处理要求,在张开量为3 mm、错台量为0 mm时,其防水能力为 0.38 MPa,错台量较大时需要对密封条断面结构进行优化设计;(2)管片接缝密封性对于嵌缝密封法的处理效果影响明显,挤压过程中嵌缝密封垫被挤出的位置、管片接缝密封性差的位置更容易出现渗漏。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
李 燚 1
2 丁文其 1
2 杨林松 3 谢东武 1
2
关键词:   
Abstract: To explore the effect and applicability of the caulking treatment measures against water leakage in shield tunnel segment joints, investigation and statistics are carried out on the segment water leakage conditions in a shield tunnel project in China. And with prepared concrete specimens the three-dimensional water pressure loading test system independently developed by Tongji University is used to carry out multiple sets of laboratory experimental study on the caulking and sealing method — the water leakage treatment measure actually used in the project.The results show that: (1) using the EPDM caulking and sealing gasket to treat the water leakage in segment joints, it can meet the requirements for Class I water-proofing. When the opening is 3 mm and the dislocation is 0 mm, it has a waterproof capacity of 0.38 MPa. When the dislocation is large, optimization design needs to be made for the section structure of the sealing gasket; (2) the sealing performance of the segment joint has obvious influence on the treatment effect of the caulking and sealing method, and water leakage is more likely to occur at positions where the caulking and sealing gasket is extruded out in the extrusion process and the sealing performance of the segment joint is poor.
KeywordsShield tunnel,   Segment joint,   Water leakage,   Caulking treatment,   Waterproof test,   EPDM sealing gas? ket     
基金资助:国家重点研发计划项目(2017YFC0806004);国家自然科学基金(51978515);上海市“科技创新行动计划”社会发展科技攻关项目(20dz1202600).
作者简介: 李 燚(1997-),男,硕士研究生,主要从事隧道与地下建筑工程方面的研究工作,E-mail: tjeduly@163.com. 通讯作者:丁文其(1969-),男,博士,教授,博士生导师,主要从事隧道及地下建筑方向的研究及教学工作,E-mail: dingwq@tongji.edu.cn.
引用本文:   
李 燚 1, 2 丁文其 1, 2 杨林松 3 谢东武 1等 .盾构隧道管片接缝渗漏水嵌缝处理试验研究[J]  现代隧道技术, 2021,V58(5): 167-172
LI Yi1, 2 DING Wenqi1, 2 YANG Linsong3 XIE Dongwu1 etc .Experimental Study on Caulking Treatment Against Water Leakage in Shield Tunnel Segment Joints[J]  MODERN TUNNELLING TECHNOLOGY, 2021,V58(5): 167-172
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2021/V58/I5/167
 
没有本文参考文献
[1] 魏 纲 1,2 赵得乾麟 1 黄 睿 1.盾构施工对邻近隧道影响的模型试验研究综述[J]. 现代隧道技术, 2021,58(5): 1-8
[2] 丁 智 1,2 何晨阳 1 张 霄 1 张文宏 3 吴 胜 4.含气土盾构施工影响及控制技术研究展望[J]. 现代隧道技术, 2021,58(5): 9-20
[3] 章龙管 1 刘绥美 1 李开富 1 徐 进 2,3,4 王胜楠 3,5 李 强 3.基于故障树与贝叶斯网络的地铁盾构施工风险预测[J]. 现代隧道技术, 2021,58(5): 21-29
[4] 郑 波 1,2 吴 剑 1,2 郑金龙 3 匡 亮 4 郭 瑞 1,2.基于现场试验的川西高海拔隧道防冻参数研究[J]. 现代隧道技术, 2021,58(5): 30-36
[5] 仇文革 万世付 高刚刚 赵海霖 戚幸鑫.砂卵石地层盾构隧道下穿铁路咽喉区地表沉降控制研究[J]. 现代隧道技术, 2021,58(5): 37-45
[6] 王志杰 1 李金宜 1 邓宇航 1 杜逸文 1 周 平 1 白小可 2 李峰刚 2.盐岩隧道施工病害揭示及致灾因子研究[J]. 现代隧道技术, 2021,58(5): 46-55
[7] 高 鑫 王文娟 李清菲 冯世杰 吴 琦.双护盾TBM步进过站路径研究[J]. 现代隧道技术, 2021,58(5): 56-64
[8] 李思明 1 禹海涛 2 薛光桥 3 徐 磊 4.穿越土-岩变化地层盾构隧道地震响应分析[J]. 现代隧道技术, 2021,58(5): 65-72
[9] 常 刚 1,2 牌立芳 3,4 庞伟军 1,4 吴红刚 1,2,4 剡理祯 1.深埋硬岩组合隧道围岩开挖变形影响研究[J]. 现代隧道技术, 2021,58(5): 73-77
[10] 陈玉坤 1 管会生 1 周 磊 2 刘 成 1.基于BP神经网络的盘形滚刀磨损预测研究[J]. 现代隧道技术, 2021,58(5): 78-84
[11] 宋 洋 1 王韦颐 2 杜春生 3.富水圆砾与泥岩复合地层泥水盾构超近接下穿既有地铁隧道掘进参数优化研究[J]. 现代隧道技术, 2021,58(5): 85-95
[12] 许有俊 1,2 黄正东 1,2 张 旭 1,2 张 朝 1,2 康佳旺 1,2 周 薇 1.大断面土压平衡矩形顶管多刀盘实测扭矩参数研究[J]. 现代隧道技术, 2021,58(5): 96-103
[13] 潘伟强 1 焦伯昌 2 柳 献 2 曾 华 3 吉茂杰 3.深埋大断面钢结构顶管接触压力及受力特性现场试验研究[J]. 现代隧道技术, 2021,58(5): 104-113
[14] 陈祉颖 牛国庆 王舒梦 郭宸玮.基于正交模拟试验的隧道空气幕参数优化研究[J]. 现代隧道技术, 2021,58(5): 114-121
[15] 潘旭东 1 白云龙 1 白云飞 2 张志强 2 廖 霖 1.富水地层冻结法施工渗流场对温度场的影响规律研究[J]. 现代隧道技术, 2021,58(5): 122-128
Copyright 2010 by 现代隧道技术