富水弱胶结地层大断面隧道施工方案优化与工程应用研究
(1.西安建筑科技大学土木工程学院,西安 710055;2.陕西省岩土与地下空间工程重点实验室,西安 710055; 3.中国铁建大桥工程局集团有限公司,天津 300300;4.中铁北京工程局集团第一工程有限公司,西安 710100)
Optimization and Application of the Construction Scheme for Large-section Tunnels in Water-rich and Weakly Cemented Strata
(1. School of Civil Engineering of Xi'an University of Architecture and Technology, Xi′an 710055; 2. Shaanxi Key Laboratory of Geotechnical and Underground Space Engineering, Xi′an 710055; 3. China Railway Construction Bridge Engineering Bureau Group Co., Ltd., Tianjing 300300; 4. The No.1 Engineering Co., Ltd. of China Railway Beijing Engineering Group, Xi′an 710100)
Download: PDF (5660KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 在富水弱胶结地层中,隧道施工极易诱发围岩坍塌或支护结构大变形。以兰渝客运专线桃树坪隧道3#斜井工区正洞段为研究背景,提出了一种适用于富水砂岩地层的“底部双导洞超前”施工工法。同时采用真空轻型井点+集水井的联合降水方案进行隧道内超前降水,以降低施工难度;采用数值分析和现场监测的方法对方案的合理性和有效性进行分析与评价。结果表明,隧道在采用“底部双导洞超前”施工工法时,拱顶沉降和净空收敛值分别为50 mm、32 mm;其支护结构上的最大接触压力为135.3 kPa;支护结构的变形和受力均在允许范围之内,隧道结构安全、稳定。“底部双导洞超前”的施工工法已成功应用于桃树坪隧道,可为后续富水弱胶结地层或软弱岩层中的超大断面隧道施工提供参考和借鉴。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
王怀正 1 宋战平 1
2 张学文 3 田小旭 1
2 潘红伟 4
关键词隧道工程   富水弱胶结地层   底部双导洞超前工法   数值分析   现场监测     
Abstract: In water-rich and weakly cemented strata, tunnel construction is very likely to induce the collapse of the surrounding rocks or serious large deformation of the support structure. This paper puts forward the lower double pilot tunnel construction method applicable for water-rich sandstone strata condition, based on the main tunnel construction of the 3# inclined shaft of the Taoshuping Tunnel on the Lanzhou-Chongqing Passenger Dedicated Line.Meanwhile, it adopts an integrated dewatering scheme of vacuum light well point + water collection well for advanced dewatering of the tunnel to reduce the construction difficulties. Using numerical analysis and on-site monitoring method, it analyzes and evaluates the reasonableness and effectiveness of the construction scheme. The results show that when the lower double pilot tunnel construction method is used, the vault settlement and clearance convergence are 50 mm and 32 mm respectively, while the maximum contact pressure on the support structure is 135.3 kPa, and the deformation and stress of the support structure are both within the acceptable range with the tunnel structure being safe and stable. The lower double pilot tunnel construction method has been successfully applied to the Taoshuping Tunnel, providing references for the construction of extra-large section tunnels in water-rich and weakly cemented strata or soft rock strata.
KeywordsTunnelling ,   Water-rich and weakly cemented strata,   Lower double pilot tunnel construction method,   Numerical analysis,   Site monitoring     
基金资助:陕西省创新能力支撑计划-创新团队(2020TD-005);陕西省住房城乡建设科技计划项目(2019-K39)
作者简介: 王怀正(1997-),男,硕士研究生,主要从事隧道施工技术方面的研究工作,E-mail:wanghzzy@163.com. 通讯作者:宋战平(1974-),男,博士,教授,博士生导师,主要从事隧道与地下工程方面的教学和研究工作,E-mail:songzhpyt@xauat.edu.cn.
引用本文:   
王怀正 1 宋战平 1, 2 张学文 3 田小旭 1, 2 潘红伟 4 .富水弱胶结地层大断面隧道施工方案优化与工程应用研究[J]  现代隧道技术, 2022,V59(2): 210-219
WANG Huaizheng1 SONG Zhanping1, 2 ZHANG Xuewen3 TIAN Xiaoxu1, 2 PAN Hongwei4 .Optimization and Application of the Construction Scheme for Large-section Tunnels in Water-rich and Weakly Cemented Strata[J]  MODERN TUNNELLING TECHNOLOGY, 2022,V59(2): 210-219
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2022/V59/I2/210
 
没有本文参考文献
[1] 王 升1,2,3,4 韦 芹1,2 李利平3.隧道突水突泥灾变机理研究现状及发展趋势[J]. 现代隧道技术, 2025,62(4): 15-25
[2] 邹育麟1, 2 刘 静1 汪 波2 陈子全2 谢作栋2 古 浩3 王楷越2.四川沿江高速公路隧道涌水突泥灾害成因分析及防治对策研究[J]. 现代隧道技术, 2025,62(3): 259-269
[3] 秦天戈1, 2 吴 立2 陈 倩1 夏 振1 刘诗雅1, 2 蔡 新1.钻爆法隧道智能建造体系研究现状与发展趋势[J]. 现代隧道技术, 2025,62(3): 1-10
[4] 王敬勇1,2 王 平2 杨 锦2 吉 锋3.基于物理模型试验的碳质千枚岩隧道支护结构优化研究[J]. 现代隧道技术, 2025,62(3): 160-169
[5] 王帅帅1 傅一帆2,3 徐 勇1 史经峰1 郭 春2,3.通过接力风机进行风量分配的隧道施工风仓式通风参数研究[J]. 现代隧道技术, 2025,62(3): 240-248
[6] 张美宁1,2 宋战平1,2,3 岳 波4 李 旭1,2,3 赵祎睿2 陶 磊5.基于实时图像与超前地质信息的隧道围岩快速分级模型构建及应用研究[J]. 现代隧道技术, 2025,62(2): 87-97
[7] 张昕阳1,2 申玉生1,2 常铭宇1,2 刘 童1,2 孙天赦3,4 胡 帅3,4.克泥效工法对泥岩地层盾构隧道地表变形控制规律研究[J]. 现代隧道技术, 2025,62(2): 283-290
[8] 陈 旺1 彭焱锋1 刘维正2 张思宇2 陈常辉1.三孔顶管上穿施工对既有隧道与地表变形影响分析[J]. 现代隧道技术, 2025,62(1): 170-182
[9] 王浩鱇1,2 申玉生1,2 潘笑海1,2 常铭宇1,2 张昕阳1,2 粟 威3.强震区穿越多破裂面破碎带隧道动力特性试验研究[J]. 现代隧道技术, 2025,62(1): 212-220
[10] 杨存斌1,2 任 洋1,2 吴岳华1,2 何万超1,2 李天斌1,2.基于M-LSTM法的隧道围岩地质信息动态智能预测研究[J]. 现代隧道技术, 2025,62(1): 74-82
[11] 王立川1,2 葛立辉3 王海彦2 孔 超4 李庆斌1 王云涛3 刘玉飞1.隧道二次衬砌拱部脱空纵向同步灌浆施工方法[J]. 现代隧道技术, 2024,61(6): 269-277
[12] 张成友1 汪 波1 杜泽昊1 高筠涵1 谭力豪2.不同锚杆支护体系防岩爆适宜性分析与锚杆参数优化研究[J]. 现代隧道技术, 2024,61(6): 64-73
[13] 张昕阳1,2 申玉生1,2 常铭宇1,2 王浩鱇1,2 潘笑海1,2 王岩岩1,2.基于GA-BP神经网络的隧道围岩相似材料配合比设计[J]. 现代隧道技术, 2024,61(6): 82-91
[14] 惠 强1 高 峰1,2 谭绪凯1 尤冬梅1.基于分层位错理论的穿越活动断层隧道结构损伤特征研究[J]. 现代隧道技术, 2024,61(6): 35-44
[15] 许晓静1, 2 宋战平1, 2, 3 田小旭1, 2 丁立波4 孙引浩5 赵俊波1, 2.基于增量法的隧道洞口边坡微型钢管桩-锚杆支护效果分析[J]. 现代隧道技术, 2024,61(6): 118-128
Copyright 2010 by 现代隧道技术