软土地层小半径盾构隧道下穿在建高铁地基加固效果研究

Research on the Effect of Foundation Reinforcement of Small-radius Shield Tunnels in Soft Soil Stratum Crossing under High-speed Rail under Construction

  • 摘要: 以福州地铁5号线盾构下穿在建福厦高铁为工程背景,针对软土地层小半径曲线盾构隧道下穿高铁高填方路基交叉施工工程的特殊性,利用现场监测数据对交叉施工全过程展开分析,研究该类工程地基加固效果及施工变形规律。结果表明,该工程若采用预应力混凝土管桩进行地基加固,后期地铁盾构施工不具备施工条件,需施作桩板结构进行地基处理;采用桩板结构对软土区域进行加固处理后,实测数据中最大地表沉降量为5.6 mm,为地表沉降控制值的18.67%,在可控范围内;提前进行地基加固后,当盾构隧道下穿施工时,路基不同位置处仅发生微小沉降,说明桩板结构加固对交叉施工变形有很好的控制效果;随着路基填筑高度增大,各层土压力值整体呈增大趋势,各层土压力变化速率呈“双峰曲线”,路基中间位置的土压力值比靠近两侧的土压力值大;盾构隧道下穿前,桩板结构混凝土支撑轴力的变化大致可分为“线性增长—过渡—再增长—稳定”4个阶段,当盾构下穿后,混凝土支撑轴力有小幅增大,后期逐渐趋于稳定。从监测数据分析可以看出,桩板结构的加固效果显著。

     

    Abstract: Taking as a research case the shield tunnel of Line 5 of the Fuzhou Metro crossing under the Fuzhou-Xia? men High-speed Railway (under construction), the on-site monitoring data were used to analyze the full process of Crossing construction according to the characteristics of the small-diameter curved shield tunnel in a soft soil stratum crossing under the high-fill subgrade of high-speed rail, so as to research the effect of foundation reinforcement of such projects and the law of construction deformation. The results show that if prestressed concrete pipe piles are used for foundation reinforcement of this project and construction conditions are not available in the metro shield construction at a later stage, the pile-slab structure should be constructed for foundation treatment; after the pileslab structure is used for reinforcement in the soft soil area, the maximum ground settlement is 5.6 mm in the measured data, accounting for 18.67% of the ground settlement control value, which is in the controllable range; after foundation reinforcement is conducted in advance, only slight settlement occurs in different positions of the subgrade in case of undercrossing construction of the shield tunnel, indicating that the reinforcement of pile-slab structure has a very good effect on controlling crossing construction deformation; as the subgrade filling height increases,the soil pressure value of each layer shows an overall increase, and the rate of change in the soil pressure of each layer shows the "bimodal curve" and the soil pressure value in the middle of the subgrade is higher than that close to both sides; before the shield tunnel crosses under the high-speed rail, the change in the axial force of concrete support of the pile-slab structure is roughly split into 4 stages: "linear growth - transition - regrowth - stability", and after the shield tunnel crosses, the axial force of concrete support slightly increases and gradually becomes stable at a later stage. It can be seen from the analysis of monitoring data that the reinforcement effect of pile-slab structure is significant.

     

/

返回文章
返回