现代隧道技术 2024, Vol. 61 Issue (6) :139-147    DOI:
数值分析与计算 最新目录 | 下期目录 | 过刊浏览 | 高级检索 << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
并行盾构下穿CFG桩加固高铁路基的沉降规律研究
(1.深圳大学土木与交通工程学院,深圳 518061;2.中国水利水电第八工程局有限公司,长沙 410004; 3.深圳大学滨海城市韧性基础设施教育部重点实验室,深圳 518061; 4.深圳市地铁地下车站绿色高效智能建造重点实验室,深圳 518061)
Study on Settlement Patterns of the CFG Pile-reinforced High-speed Railway Subgrade Caused by Parallel Shield Tunnelling
(1. College of Civil and Transportation Engineering, Shenzhen University, Shenzhen 518061;2. Sinohydro Bureau 8 Co., Ltd., Changsha 410004; 3. Key Laboratory for Resilient Infrastructures of Coastal Cities (Shenzhen University), MOE, Shenzhen 518061; 4. Shenzhen Key Laboratory of Green, Efficient and Intelligent Construction of Underground Metro Station, Shenzhen 518061)
Download: PDF (5399KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要  以西安地铁1号线盾构隧道下穿徐兰高铁为研究背景,对盾构下穿CFG桩加固高铁路基前后的现场轨道沉降监测数据进行统计分析,并采用Plaxis-3D软件建立并行盾构隧道下穿高铁路基的精细化三维有限元模型,通过与现场实测数据对比验证数值模型的有效性。在此基础上,分析盾构隧道施工引起的轨道-路基-水泥粉煤灰碎石桩(CFG桩)-土体-盾构隧道系统的沉降传递规律,探究CFG桩的受力变形。研究结果表明,盾构施工完全通过下穿段后在地表形成50 m长的沉降槽,沉降分布曲线为双驼峰;CFG桩底部在盾构隧道穿越高铁路基后变得松散,最终实际有效桩长为原长的75%;通过研究不同位置的CFG桩,确定依托工程中横断面上CFG桩出现松散的范围具体为(-12.6 m,12.6 m)。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
吴贝钰1 谢渭平2 林星涛1
3
4 高 晨2 苏 栋1
3
4 陈湘生1
3
4
关键词盾构隧道   下穿高铁路基   CFG桩-土结构   沉降   CFG桩有效桩长     
Abstract: Focusing on the shield tunnelling of the Xi′an Metro Line 1 beneath the Xuzhou-Lanzhou High-speed Railway, this study performs a statistical analysis of the monitored track settlement data before and after the tunnelling. A refined three-dimensional finite element model of parallel shield tunnelling crossing under a high-speed railway subgrade is established using Plaxis-3D software. The numerical model′s validity is verified through comparison with field measurements. Based on the model, the settlement transfer mechanism of the track-subgradeCFG pile-soil-shield tunnel system induced by shield tunnelling is analyzed, and the stress and deformation behaviors of CFG piles are investigated. Research results indicate that when the shield tunnel completely passes through the railway subgrade, a 50 m long surface settlement trough forms, with a double-peak distribution curve. The bottom of CFG piles becomes loose after shield tunnelling beneath the railway subgrade, resulting in an effective pile length of 75% of the original length. The range of loosening in CFG piles in the horizontal and longitudinal sections of this project is determined as (-12.6 m, 12.6 m) by studying CFG piles at different positions.
KeywordsShield tunnel,   Tunnelling beneath high-speed railway subgrade,   CFG pile-soil structure,   Settlement; Effective pile length of CFG piles     
基金资助:国家自然科学基金项目(52378308, 52208355).
作者简介: 吴贝钰(1997-),男,硕士研究生,主要从事盾构近接施工控制方面的研究工作,E-mail: 1067140241@qq.com. 通讯作者:林星涛(1990-),男,博士,助理教授,主要从事盾构掘进土拱效应、盾构近接施工控制等方面的研究工作,E-mail: xtlin@szu.edu.cn.
引用本文:   
吴贝钰1 谢渭平2 林星涛1, 3, 4 高 晨2 苏 栋1等 .并行盾构下穿CFG桩加固高铁路基的沉降规律研究[J]  现代隧道技术, 2024,V61(6): 139-147
WU Beiyu1 XIE Weiping2 LIN Xingtao1, 3, 4 GAO Chen2 SU Dong1 etc .Study on Settlement Patterns of the CFG Pile-reinforced High-speed Railway Subgrade Caused by Parallel Shield Tunnelling[J]  MODERN TUNNELLING TECHNOLOGY, 2024,V61(6): 139-147
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2024/V61/I6/139
 
没有本文参考文献
[1] 张小龙.桩基荷载作用下地铁盾构隧道结构力学响应分析[J]. 现代隧道技术, 2025,62(4): 82-89
[2] 郭永军1 李 超2 郑建国3 于永堂4 朱才辉5.地面堆载对西安黄土地层中既有盾构管片影响研究[J]. 现代隧道技术, 2025,62(4): 61-72
[3] 周弋力1 封 坤1 郭文琦1 张亮亮2 李春林3.超大直径盾构隧道管片纵缝抗弯力学行为与损伤过程研究[J]. 现代隧道技术, 2025,62(4): 163-173
[4] 易 丹1 薛皓匀2 杨绍毅2 喻 波1 封 坤2 林 刚1.盾构隧道管片结构螺栓失效对横向地震响应的影响分析[J]. 现代隧道技术, 2025,62(4): 174-181
[5] 贾永刚1 郝子晗1 鲁卫东1 吴 帆1 阳卫卫2.钢纤维混凝土管片不同接头型式力学性能研究[J]. 现代隧道技术, 2025,62(4): 182-196
[6] 谭鑫雨1 韦 猛1,2 兰灵申1 尚 强1 张海涛1.盾构刀盘结泥饼土体降黏附试验与机理研究[J]. 现代隧道技术, 2025,62(4): 219-229
[7] 刘朋飞1,2 曾德星2 王 霄3 杨 钊2 李 钰2.盾构泥饼分解剂作用效果评价试验及应用研究[J]. 现代隧道技术, 2025,62(4): 230-237
[8] 胡云进1,,2,3 朱铭伟1,2,3 郜会彩1,2,3 任智豪1,2,3.地下水渗流对能源盾构隧道换热性能的影响[J]. 现代隧道技术, 2025,62(3): 50-59
[9] 李瀚源1,2 冯 劲1 郭洪雨1 谢雄耀2 周红升1 孙 飞1.海底盾构隧道双层衬砌结构联合承载力学特性研究[J]. 现代隧道技术, 2025,62(3): 126-138
[10] 张昕阳1,2 申玉生1,2 常铭宇1,2 刘 童1,2 孙天赦3,4 胡 帅3,4.克泥效工法对泥岩地层盾构隧道地表变形控制规律研究[J]. 现代隧道技术, 2025,62(2): 283-290
[11] 宋战平1,2,3 李雪莉1 张玉伟1,2,3 钟仕明1 石 卫4.我国地铁车站暗挖工法综述与展望[J]. 现代隧道技术, 2025,62(2): 1-15
[12] 于同生1,2 官林星3 闫治国1,2.地铁盾构隧道多灾害场景及结构多灾害响应研究综述[J]. 现代隧道技术, 2025,62(2): 16-26
[13] 朱叶艇1,2 朱雁飞1 王志华1,3 王帅峰4 王 浩1 马志刚1 龚 卫1,2 秦 元1.推力矢量智控盾构的理论创新、方法实现与工程验证[J]. 现代隧道技术, 2025,62(2): 71-78
[14] 肖明清1 封 坤2 薛光桥1 王运超2 鲁志鹏1 陈 龙2.软土地层盾构姿态偏移引起的附加土压力影响因素研究[J]. 现代隧道技术, 2025,62(2): 141-150
[15] 姚占虎1 杨 琴2 李 辉2 魏代伟2 孟 佳2.盾构隧道同步双液注浆技术研究与应用[J]. 现代隧道技术, 2025,62(2): 265-273
Copyright 2010 by 现代隧道技术