MODERN TUNNELLING TECHNOLOGY 2020, Vol. 57 Issue (2) :176-183    DOI:
Current Issue | Next Issue | Archive | Adv Search << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
Engineering Measures and Safety Evaluation of Baizhang Tunnel Passing through Flow Plastic Water-rich Fracture Zone
(1 Sichuan Highway Planning Survey, Design and Research Institute Ltd., Chengdu 610041; 2 Southwest Jiaotong University,MOE Key Laboratory of Transportation Tunnel Engineering, Chengdu 610031)
Download: PDF (2777KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract Collapse and clearance invasion events occurred repeatedly during the construction at the section of ZK152+433-ZK152+463 of left tube of Baizhang tunnel passing through a flow-plastic fracture zone with abundant water, which brought unprecedented challenges to the engineers. The various measures adopted in the construction are described in detail, and an analysis on structure safety is conducted by numerical method. The results show that:(1) as for the flow-plastic water-rich fracture zone, dense advance support is the most effective measure to prevent large deformation or collapse of surrounding rocks during excavation, a ring of ?51 self-drilling anchor bolts with unit length of 3.5 m are installed between steel arches (with the steel arch interval of 50 cm), that is to say there are 7 layers of advance support for each tunnel section, effectively controlling the rock mass deformation after excavation, avoiding collapse and clearance invasion of tunnel lining; (2) it is significant to reinforce the surrounding rocks,especially at sidewall and tunnel floor, since it can effectively decrease the integral subsidence of tunnel lining during construction. A combination of jackstone treatment and grouting is adopted to reinforce the surrounding rocks at sidewall and tunnel floor and the effect is much better than that only with grouting; (3) as for the tunnel with explicit external load, the parameters of lining support should be determined by both calculation analysis and engineering experience, which will guarantee the safety of tunnel structure and also make it economical and reasonable; (4) as for the two-lane tunnel, three-bench method is taken and the bench length should be shortened as much as possible in order to form an enclosure of primary support in time so as to control the deformation of surrounding rocks better.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
TIAN Zhiyu1 TIAN Shangzhi1 YANG Feng1 ZHANG Zhaojie1 WANG Bo2
KeywordsTunnel   Flow-plastic water-rich fracture zone   Clearance invasion   Collapse   Treatment measure   Nu? merical analysis   Experience summarization     
Abstract: Collapse and clearance invasion events occurred repeatedly during the construction at the section of ZK152+433-ZK152+463 of left tube of Baizhang tunnel passing through a flow-plastic fracture zone with abundant water, which brought unprecedented challenges to the engineers. The various measures adopted in the construction are described in detail, and an analysis on structure safety is conducted by numerical method. The results show that:(1) as for the flow-plastic water-rich fracture zone, dense advance support is the most effective measure to prevent large deformation or collapse of surrounding rocks during excavation, a ring of ?51 self-drilling anchor bolts with unit length of 3.5 m are installed between steel arches (with the steel arch interval of 50 cm), that is to say there are 7 layers of advance support for each tunnel section, effectively controlling the rock mass deformation after excavation, avoiding collapse and clearance invasion of tunnel lining; (2) it is significant to reinforce the surrounding rocks,especially at sidewall and tunnel floor, since it can effectively decrease the integral subsidence of tunnel lining during construction. A combination of jackstone treatment and grouting is adopted to reinforce the surrounding rocks at sidewall and tunnel floor and the effect is much better than that only with grouting; (3) as for the tunnel with explicit external load, the parameters of lining support should be determined by both calculation analysis and engineering experience, which will guarantee the safety of tunnel structure and also make it economical and reasonable; (4) as for the two-lane tunnel, three-bench method is taken and the bench length should be shortened as much as possible in order to form an enclosure of primary support in time so as to control the deformation of surrounding rocks better.
KeywordsTunnel,   Flow-plastic water-rich fracture zone,   Clearance invasion,   Collapse,   Treatment measure,   Nu? merical analysis,   Experience summarization     
Cite this article:   
TIAN Zhiyu1 TIAN Shangzhi1 YANG Feng1 ZHANG Zhaojie1 WANG Bo2 .Engineering Measures and Safety Evaluation of Baizhang Tunnel Passing through Flow Plastic Water-rich Fracture Zone[J]  MODERN TUNNELLING TECHNOLOGY, 2020,V57(2): 176-183
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2020/V57/I2/176
 
No references of article
[1] MA Hui1 GAO Mingzhong2.Discussion on the Construction Management of Sichuan-Tibet Railway Tunnel Based on System Engineering Methodology[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 1-8
[2] WANG Mingnian1,2 GUO Xiaohan1,2 YU Li1,2 LI Chunhui1,2 CHEN Shuwang3.Study on the Location Selection of Emergency Rescue Station of the Extra-long Railway Tunnel at High Altitude[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 9-14
[3] LI Chang1,2 WANG Gang1,2 QIU Wenge1,2,3 GONG Lun1,2 ZHAO Yingchun4 WANG Qiuhui4.Research and Application of Support Resistant Limiting Dampers in the Tunnel with High Horizontal Geostress[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 15-29
[4] LIAO Jun1 DONG Qian1 LIANG Hongyong2 JIAN Bo2 SHI Yuchuan1,3 GONG Hongwei1.Preliminary Study on the Classification Indexes of Surrounding Rock for the Highway Tunnel in Nearly Horizontal Red-bed Stratum[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 25-29
[5] LU Song1,2 WANG Xu1,2 LI Cangsong1,2 MENG Lu1,2.Study on Geological Prediction Technology of HSP Method for TBM Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 30-35
[6] ZHONG Zuliang1,2 GAO Guofu1, 2 CHEN Peng1 YAN Ru1.Discussion on Design for the Liangjiang Ship Sightseeing Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 36-42
[7] HUANG Fujie HE Zegan ZHANG Weimin LIU Shanshan.Application Research of BIM Technology in Engineering Design of the Immersed Tube Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 43-48
[8] TANG Xiaosong1, 2 ZHENG Yingren3 WANG Yongfu1.Application of FEM Strength Reduction Method in Stability Analysis and Control of Tunnel Construction[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 49-55
[9] WU Bo1,2 LAN Yangbin1,2 YANG Shisheng1,2 YANG Jianxin3 PANG Xiaoyu3.Study on Stability of Surrounding Rock Based on Strength Reduction Dynamic Analysis Method[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 56-64
[10] ZHOU Cuiying1,2 LI Ang2,3 LIU Zhen1,2.Study on the Influence of Parallel Fold Structure on Deformation of Tunnel Surrounding Rocks[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 65-74
[11] MA Li1 LIU Yapeng2 LI Sheng3,4 LV Wenda5 XIE Chao3,4 DAI Jinpeng3,4.Study on the Mechanical Behaviors of High-filled Loess Arched Open Cut Tunnel under Different Load Reduction Measures[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 75-84
[12] ZHANG Bingwu1 ZHANG Peng1 DAI Zhenhua2 WU Yinghe2 LUO Wei2.Analysis of the Mechanical Behavior of Segments of the Shield-driven Metro Tunnel beneath River Bottom[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 85-90
[13] SUI Xin1 ZHANG Zhengwei1 MING Xuan2 DOWNIE Steven3 PADHANI Shahid3 ZHAO Libo4.Numerical Simulation Analysis of SF6 Gas Leakage in Extra-Long GIL Utility Tunnel[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 91-98
[14] ZHANG Kefeng.Numerical Simulation of Water Burst in Roadway Excavation with Karst Cave Ahead[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 99-107
[15] ZHANG Yan1, 2 WANG Wei2 DENG Xueqin2.Prediction Model of TBM Advance Rate Based on Relevance Vector Machine[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(3): 108-114
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY