北山螺旋斜坡道TBM施工直线段与曲线段滚刀磨损对比分析
(1.北京工业大学 城市防灾与减灾教育部重点实验室,北京 100124; 2.核工业北京地质研究院,北京 100029;
3.中国国家原子能机构高放废物地质处置创新中心,北京 100029)
Comparative Analysis of Disc Cutter Wear in Straight and Curved Sections during TBM Excavation of the Beishan Spiral Ramp#br#
(1. Key Laboratory of Urban Security and Disaster Engineering of Ministry of Education, Beijing University of Technology,
Beijing 100124; 2. Division of Environmental Engineering, Beijing Research Institute of Uranium Geology, Beijing 100029;
3. CAEA Innovation Center for Geological Disposal of High-Level Radioactive Waste, Beijing 100029)
Download: PDF (6571KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 为分析螺旋型隧道TBM施工中滚刀磨损规律,通过收集北山螺旋斜坡道TBM施工滚刀更换与磨损数据,并跟踪获取斜坡道沿线岩体数据,对比分析直线段与曲线段的滚刀更换数量、累积磨损量以及相同围岩条件下的滚刀磨损速率。研究结果表明,曲线段施工中单位掘进距离的滚刀消耗量显著高于直线段,尤其是中心刀异常失效比例增加,以及边刀磨损速率升高;结合滚刀在两种线形中的磨损机理发现,滚刀在曲线段工作时受力不均衡,边刀侧向力显著增加,从而导致其磨损速率增加。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
项 瑜1 龚秋明1 谢兴飞1 黄 流1 王 驹2
3 马洪素2
3
关键词隧道掘进机   直线段   曲线段   滚刀磨损速率     
Abstract: In order to analyze the wear characteristics of disc cutters during TBM construction in spiral tunnels, the cutter replacement and wear data obtained from the TBM excavation of the Beishan spiral ramp were collected, and the surrounding rock data along the ramp were obtained. A comparative analysis was conducted on the number of cutter replacements, cumulative cutter wear, and cutter wear rate under similar surrounding rock conditions in straight and curved sections. The results show that the cutter consumption per unit advance in curved sections is significantly higher than that in straight sections, especially the increase in abnormal failure proportion of center cutters and the increase in wear rate of edge cutters. Combined with the wear mechanism of cutters under the two alignment conditions, it is found that the cutters are subjected to unbalanced forces in curved sections, and the lateral forces on edge cutters increase significantly, resulting in an increase in their wear rate.
KeywordsTunnel boring machine (TBM),   Straight section,   Curved section,   Disc cutter wear rate     
引用本文:   
项 瑜1 龚秋明1 谢兴飞1 黄 流1 王 驹2, 3 马洪素2, 3 .北山螺旋斜坡道TBM施工直线段与曲线段滚刀磨损对比分析[J]  现代隧道技术, 2025,V62(5): 78-
XIANG Yu1 GONG Qiuming1 XIE Xingfei1 HUANG Liu1 WANG Ju2, 3 MA Hongsu2, 3 .Comparative Analysis of Disc Cutter Wear in Straight and Curved Sections during TBM Excavation of the Beishan Spiral Ramp#br#[J]  MODERN TUNNELLING TECHNOLOGY, 2025,V62(5): 78-
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2025/V62/I5/78
 
没有本文参考文献
[1] 张 欢1,2 张世殊3 李天斌1,2 杨 罡1,2 李世森1,2 肖华波3 陈卫东3.基于GAPSO-LightGBM的TBM施工隧道围岩等级智能预测方法[J]. 现代隧道技术, 2025,62(2): 98-109
[2] 贺泊宁.全断面隧道掘进机导向定位技术综述[J]. 现代隧道技术, 2025,62(1): 1-9
[3] 耿 麒1 黄登侠2 陈建勋3 刘伟伟3 罗彦斌3 马茂勋1 李晓斌1李 鹏2 乔浩利2.新型楔平组合式TBM滚刀切削极硬岩性能研究[J]. 现代隧道技术, 2025,62(1): 114-124
[4] 杨银伟1 王宝友1 王立川1,2 王峥峥3 耿 麒4 章慧健2 冀国栋1.TBM带式输送机出渣技术经济比较研究[J]. 现代隧道技术, 2024,61(4): 119-125
[5] 叶复萌 1 于庆增 2 贺 飞 2 张 啸 2.抽水蓄能电站地下洞室集群修建TBM关键技术研究与应用[J]. 现代隧道技术, 2023,60(2): 14-21
[6] 宁向可 1 耿 麒 2 卢智勇 2 于庆增 1.全断面隧道掘进机锥面刀盘滚刀破岩机制研究[J]. 现代隧道技术, 2023,60(2): 73-83
[7] 耿 麒 1 张兴宇 1 贺 飞 2 齐志冲 2 汪学斌 1 叶 敏 1 张大庆 3.TBM两级螺旋式刀盘出渣机制数值模拟研究[J]. 现代隧道技术, 2023,60(2): 84-93
[8] 阮承志.盾构隧道管片排版分析方法研究[J]. 现代隧道技术, 2021,58(4): 224-228
[9] 李 港 1 李晓军 1 杨文翔 2 韩 冬 1.基于深度学习的TBM掘进参数预测研究[J]. 现代隧道技术, 2020,57(5): 154-159
[10] 闫长斌 姜晓迪.基于岩体指标和掘进参数的TBM净掘进速率预测模型[J]. 现代隧道技术, 2020,57(2): 26-33
[11] 刘路.TBM胶带输送系统硫化及故障分析[J]. 现代隧道技术, 2011,48(3): 144-147