箱式隧道现浇大体积混凝土温度应力场及裂缝控制研究
(1重庆交通大学,重庆 400074;2山区公路水运交通地质减灾重庆市高校市级重点实验室,重庆 400074)
Study on Thermal Stress Field and Cracking Control of Cast-in-situ Mass Concrete in a Box Tunnel
(1 Chongqing Jiaotong University, Chongqing 400074; 2 Key Municipal Laboratory of Chongqing Colleges for Geological Disaster Reduction in Highway and Water Transportation in Mountainous Areas, Chongqing 400074)
Download: PDF (4124KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 大体积混凝土开裂问题一直以来都是工程界亟需解决的研究课题。基于此,文章以江苏省徐州市山体修复项目中的箱式多跨连拱隧道现浇大体积混凝土为研究背景,通过在隧道大体积混凝土浇筑过程中设置温度监测点实测其温度,并利用ABAQUS有限元软件的二次开发功能建立隧道单跨有限元模型进行混凝土温度应力场的模拟分析,考虑改变混凝土入模温度、养护温度、拆模时间及分层浇筑层数等因素,对隧道大体积混凝土的中心点温度峰值、最大里表温差及表面拉应力进行分析,总结出隧道大体积混凝土浇筑温度应力场的变化规律。结果表明:模拟得到的温度值与现场实测温度值的变化规律基本一致;混凝土入模温度和养护温度上升20 ℃,中心点温度峰值分别增大8.47 ℃和10.48 ℃,最大里表温差分别增大6.35 ℃和下降6.79 ℃,表面拉应力分别增大0.61 MPa和减小0.52 MPa;浇筑后约3 d(混凝土开始降温时)进行拆模养护,能使中心点温度峰值、最大里表温差及表面拉应力最小;采用合适的分层浇筑层数也有利于大体积混凝土裂缝控制。根据模拟结果制定的现场控制裂缝措施,有效控制了混凝土结构的裂缝产生,取得了良好的实际效果。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
傅奕帆 1
2 王林峰 1
2 程 平 1
2 唐 宁 1
2 周 楠 1
2
关键词:   
Abstract: Cracking in mass concrete has always been an urgent research topic in the engineering field. So, in this paper, taking the cast-in-situ mass concrete of a multi-span multi-arch box tunnel in the Mountain Restoration Project in Xuzhou City, Jiangsu Province as the research background, temperature monitoring points are installed and the temperature at each monitoring point is measured during the pouring process of mass concrete, and then the secondary development function of ABAQUS finite element software is adopted to establish a finite element model of the single span tunnel, so as to simulate the thermal stress field of the mass concrete. Meanwhile, taking into consideration of the variations of concrete molding temperature, curing temperature, formwork removal time, pouring layer and so on, it analyzes the peak temperature at the center point, the maximum temperature difference between the core and surface as well as the surface tensile stress of the mass concrete in the tunnel. Finally, the variation law is concluded for thermal stress field of cast-in-situ mass concrete in the tunnel. The results show that: the variation law of the simulated temperature is basically consistent with the one measured on the site; when the concrete molding temperature and curing temperature increase by 20 ℃ , the peak temperature at the central point increases by 8.47 ℃ and 10.48 ℃, respectively, the maximum temperature difference between the core and surface increases by 6.35 ℃ or decreases by 6.79 ℃, respectively, and the tensile stress on the surface increases by 0.61 MPa or decreases by 0.52 MPa, respectively; Formwork removal and curing should be carried out about 3 days after pouring (when the concrete began to cool down) to minimize the peak temperature at the central point, the maximum temperature difference on inner surface and the tensile stress on the surface; the appropriate number of pouring layers is also conducive to the cracking control of the mass concrete. The on-site cracking control measures formulated according to the simulation results could effectively control the cracks of concrete structure and achieve good practical results.
KeywordsBox tunnel,   Cast-in-situ mass concrete,   ABAQUS secondary development,   Thermal stress field,   Analy? sis of influencing factors,   Crack control     
基金资助:基金项目:重庆市自然科学基金面上项目(cstc2020jcyj-msxmX0218);重庆市教委科学技术研究项目(KJQN201800706).
作者简介: 作者简介:傅奕帆(1996-),男,硕士研究生,主要从事岩土与地下工程领域的相关研究工作,E-mail: 584048612@qq.com. 通讯作者:王林峰(1983-),男,博士,教授,主要从事岩土与地下工程领域的相关研究及教学工作,E-mail: wanglinfeng@cqjtu.edu.cn.
引用本文:   
傅奕帆 1, 2 王林峰 1, 2 程 平 1等 .箱式隧道现浇大体积混凝土温度应力场及裂缝控制研究[J]  现代隧道技术, 2021,V58(6): 173-181
FU Yifan1, 2 WANG Linfeng1, 2 CHENG Ping1 etc .Study on Thermal Stress Field and Cracking Control of Cast-in-situ Mass Concrete in a Box Tunnel[J]  MODERN TUNNELLING TECHNOLOGY, 2021,V58(6): 173-181
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2021/V58/I6/173
 
没有本文参考文献
[1] 李瑞俊1 宋宗莹2 李 琛1 王文斌2 任育珍3,4 蔡建华3,4 张家旭3,4.重载铁路梁家山隧道病害多源融合诊断与处置对策[J]. 现代隧道技术, 2025,62(4): 301-308
[2] 张小龙.桩基荷载作用下地铁盾构隧道结构力学响应分析[J]. 现代隧道技术, 2025,62(4): 82-89
[3] 李克玺1,2 党建东3 张 见3 叶光祥4 王晓军1,2 陈青林1,2 曹世荣2 张 河1,2.基于声发射特征参数的不同类型砂岩破裂特征研究[J]. 现代隧道技术, 2025,62(4): 26-36
[4] 周彩荣1 易黎明1 马山青2 周 蠡3 于金弘4,5.三点加载下高性能纤维混凝土顶管承载特性及配筋方案研究[J]. 现代隧道技术, 2025,62(4): 50-60
[5] 郭永军1 李 超2 郑建国3 于永堂4 朱才辉5.地面堆载对西安黄土地层中既有盾构管片影响研究[J]. 现代隧道技术, 2025,62(4): 61-72
[6] 王永刚1 崔翌堃1 吴九七2,3 黄 俊4 沈 翔2,3 杨 奎4 苏 栋2,3.考虑不同磨损形式下的滚刀受力与磨损对比分析[J]. 现代隧道技术, 2025,62(4): 73-81
[7] 冯冀蒙1,2 宋佳黛1,2 王圣涛3 李艺飞1,2 张俊儒1,2 王好明4 汪 波1,2.填海地层特大断面隧道超长管棚变形控制 效能研究[J]. 现代隧道技术, 2025,62(4): 155-162
[8] 徐才坚1 陈星宇1 雷明林1 张兴龙2 孙怀远2 李晓军2.隧道施工掌子面前方围岩富水性数字孪生与风险决策[J]. 现代隧道技术, 2025,62(4): 90-99
[9] 杨 颖1 倪 凯1 葛 林2 张明飞3 王晓睿4.弱光条件下基于改进Unet模型的隧道渗水病害图像分割[J]. 现代隧道技术, 2025,62(4): 100-110
[10] 苏开春1 付 锐2,3 曾弘锐2,3 冷希乔4 郭 春2,3.基于DBO-A-LSTM的公路隧道短时多步交通量预测[J]. 现代隧道技术, 2025,62(4): 111-121
[11] 熊 颖1,2 张俊儒1,2 范子焱1,2 陈佳豪1,2 马荐驰1,2 陈鹏涛1,2 谭瑞锋3,4.层状软岩中爆破应力波传播与振动衰减特性研究[J]. 现代隧道技术, 2025,62(4): 122-131
[12] 刘 杨1 邵泽楷2 田浩帆2 张汝溪1 郑 波3 王峥峥2.高速公路隧道下穿房柱式煤矿采空区爆破施工煤柱 损伤规律研究[J]. 现代隧道技术, 2025,62(4): 132-144
[13] 罗志洋1 张春瑜2,3 王立川1,2,4,5 徐 烁1 李利平4 王倩倩5 刘志强6.TBM裂隙岩体隧洞涌水机制及注浆堵水研究[J]. 现代隧道技术, 2025,62(4): 145-154
[14] 周弋力1 封 坤1 郭文琦1 张亮亮2 李春林3.超大直径盾构隧道管片纵缝抗弯力学行为与损伤过程研究[J]. 现代隧道技术, 2025,62(4): 163-173
[15] 易 丹1 薛皓匀2 杨绍毅2 喻 波1 封 坤2 林 刚1.盾构隧道管片结构螺栓失效对横向地震响应的影响分析[J]. 现代隧道技术, 2025,62(4): 174-181
Copyright 2010 by 现代隧道技术