Abstract:
The newly-built tunnel passing closely under the existing station will inevitably lead to settlement of the existing station, and especially deformation joints are prone to differential settlement. Based on the Suzhoujie Station of Beijing Subway Line 16 passing closely under the existing Line 10, this paper analyzes the overall settlement of the existing station and the differential settlement at deformation joints through a combination of field measurement and numerical simulation. The study results show that installing jacks significantly prevents the settlement of the existing station, after installation of jacks the settlement of the existing station is reduced by about 58%, and the jacking force of the jack shall be controlled between 180-450 t; the impact of construction on the single-deck station structure side at deformation joints is greater than that on the double-deck station structure side, the stress on the socket is gradually increased with the excavation of the lower tunnel, and reduced after installation of jacks, indicating that the jack can effectively reduce the tensile stress of the existing station and maintain the safety of the existing station; with the action of the jacking force of jacks, the settlement curve of the existing station presents a stepwise change at the jack installation points, while the upper ground surface settlement is relatively uniform.
LIANG Erbin
.Study of the Settlement Control of Deformation Joints of Tunnels Passing Closely under the Existing Station[J] MODERN TUNNELLING TECHNOLOGY, 2022,V59(2): 182-191