现代隧道技术 2023, Vol. 60 Issue (3) :175-181    DOI:
试验与监测 最新目录 | 下期目录 | 过刊浏览 | 高级检索 << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
卵砾石地层泥水盾构不同性质泥浆成膜试验研究
(1.中交隧道工程局有限公司, 北京 100088;2.河海大学岩土力学与堤坝工程教育部重点试验室,南京 210098;3.河海大学土木与交通学院,南京 210098)
Experimental Study on Filter Cake Formation in Slurry Shield Tunnelling in Cobble-gravel Stratum Using Slurries with Various Properties
(1. CCCC Tunnel Engineering Co., Ltd., Beijing 100088; 2. Key Laboratory of Ministry of Education for Geomechanics and Embankment Engineering, Hohai University, Nanjing 210098; 3. School of Civil Engineering and Transportation, Hohai University,Nanjing 210098)
Download: PDF (3313KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 针对北京南水北调团九二期工程泥水盾构穿越高渗透卵砾石层泥浆成膜问题,配制不同密度、不同砂添量的泥浆进行成膜试验,从泥浆渗透流量和泥膜渗透系数等方面对泥浆成膜效果进行分析。结果表明:在渗透系数为10-1 cm/s量级的高渗透地层,密度小于1.25 g/cm3的膨润土-黏土混合泥浆难以成膜,密度达到1.3 g/cm3的泥浆可以形成泥皮+渗透带型泥膜;而密度为1.15 g/cm3的膨润土-黏土混合泥浆添加适量砂子后,可形成泥皮+渗透带型泥膜,且渗透流量、成膜时间较未加砂子的同密度泥浆显著降低;随着砂添量的增加,泥浆渗透流量略有减少,所形成泥膜孔隙比和渗透系数也呈减小趋势;当砂添量为5%时,形成泥膜的渗透系数可达10-8 cm/s量级。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
关键词卵砾石地层   泥水盾构   泥浆   渗透流量   泥膜     
Abstract: Given the problem of filter cake formation of the slurry shield that passes through a highly permeable cobble-gravel stratum in the Tuan-Jiu Project Phase II under the South-to-North Water Diversion Project in Beijing,the slurries with different densities and different sand quantities are prepared to conduct the filter cake formation test,and the filter cake formation effect is analyzed from aspects such as slurry seepage discharge and permeability coefficient of filter cake. As the results show, in a highly permeable stratum with coefficient of permeability of 10-1 cm/s magnitude, the bentonite-clay mixed slurry with density <1.25 g/cm3 is difficult for filter cake formation, but the slurry with density of 1.3 g/ cm3 can form a slurry skin + permeation zone type filter cake. If the bentonite-clay mixed slurry with density of 1.15 g/cm3 is given a proper amount of sand, it will form a slurry skin + permeation zone type filter cake, and the seepage discharge and filter cake formation time are noticeably decreased as compared with the slurry without sand and with the same density. As more sand is added, the seepage discharge of slurry decreases slightly, and the void ratio and permeability coefficient of the formed filter cake show also the trend of decreasing.When the sand content is 5%, the permeability coefficient of the formed filter cake reaches the 10-8 cm/s magnitude.
KeywordsCobble-gravel stratum,   Slurry shield,   Slurry,   Seepage discharge,   Filter cake     
基金资助:国家自然科学基金(51778213).
作者简介: 李 辉(1986-),男,高级工程师,主要从事盾构隧道施工相关的研究及管理工作,E-mail: 477564696@qq.com
引用本文:   
.卵砾石地层泥水盾构不同性质泥浆成膜试验研究[J]  现代隧道技术, 2023,V60(3): 175-181
.Experimental Study on Filter Cake Formation in Slurry Shield Tunnelling in Cobble-gravel Stratum Using Slurries with Various Properties[J]  MODERN TUNNELLING TECHNOLOGY, 2023,V60(3): 175-181
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2023/V60/I3/175
 
没有本文参考文献
[1] 方忠强 1,2 袁 锐 3 孙统立 1,2 王登峰 3 江苏禹 4 张建峰 4 闵凡路 3.高含泥率废弃粉质土砂配制盾构壁后注浆浆液试验研究[J]. 现代隧道技术, 2023,60(3): 182-188
[2] 竺维彬 1 米晋生 1 谢文达 2 孟繁璟 2.“巨厚岩层”覆盖下泥水盾构施工沉陷原因及对策研究[J]. 现代隧道技术, 2022,59(6): 1-13
[3] 刘泓志 1,2 干聪豫 1,2 赵 亮 1,2 左世荣 1,2 张晗硕 1,2.基于地质条件变化的泥水盾构动态施工技术研究[J]. 现代隧道技术, 2022,59(3): 246-252
[4] 刘来仓 1,2 夏鹏举 3 吕焕杰 1,2 王云芝 1,2 李鹏飞 1,2 闵凡路 1,.CMC改性海水泥浆性质变化及砂地层成膜试验研究[J]. 现代隧道技术, 2022,59(1): 249-255
[5] 宋 洋 1 王韦颐 2 杜春生 3.富水圆砾与泥岩复合地层泥水盾构超近接下穿既有地铁隧道掘进参数优化研究[J]. 现代隧道技术, 2021,58(5): 85-95
[6] 陆岸典 1 肖 惠 2 沈 翔 2 付艳斌 2.狮子洋输水隧洞泥水盾构设计及施工技术分析[J]. 现代隧道技术, 2020,57(5): 226-231
[7] 乌效鸣 1 徐 晗 1 魏林春 2 迪娜·木拉提 1 程国良 3.泥水盾构泥浆除砂的选择性絮凝剂应用研究[J]. 现代隧道技术, 2020,57(3): 189-192
[8] 蒋晓天 曾英俊 刘宇宏.泥水平衡盾构穿越富水砂砾层施工技术研究[J]. 现代隧道技术, 2020,57(2): 198-203
[9] 杨 钊 1,3 贺祖浩 1,2 刘 毅 1,2 陈培帅 1,2 李德杰 1,3.福州地铁过江通道泥水盾构弃浆在壁后注浆材料中的再利用[J]. 现代隧道技术, 2019,56(3): 192-199
[10] 刘成1,2 陆杨1 刘磊1 吕伟华1.加砂泥浆在砂性地层中的堵塞机制及成膜结构分析[J]. 现代隧道技术, 2018,55(5): 245-253
[11] 孔玉清.泥水盾构环流系统及排泥管携碴能力分析与应用[J]. 现代隧道技术, 2018,55(3): 205-213
[12] 崔根群 1 刘 瑶 2.基于槽壁稳定性的地下连续墙成槽施工泥浆重度计算方法[J]. 现代隧道技术, 2018,55(1): 178-183
[13] 王助锋 1,2 冯欢欢 1,2.泥质粉砂岩地层泥水盾构防止刀盘结泥饼针对性改进[J]. 现代隧道技术, 2017,54(6): 217-222
[14] 王明胜 1 刘大刚 2, 3.顶管隧道工程触变泥浆性能试验及减阻技术研究[J]. 现代隧道技术, 2016,53(6): 182-189
[15] 钟长平1,3 竺维彬2 邱小佩4 李世佳1 陈 和2 黄威然1 周翠英3 .盾构施工“衡盾泥”辅助新工法研究[J]. 现代隧道技术, 2016,53(3): 1-7
Copyright 2010 by 现代隧道技术