Analysis of the Stress Characteristics at the Dome Type Metro Tunnel Intersection
(1. Shandong Expressway Infrastructure Construction Co., Ltd., Jinan 250000; 2. Shandong University of Science and Technology, Qingdao 266590; 3. Shandong Provincial Transportation Planning and Design Institute Group Co., Ltd., Jinan 250101)
Download: PDF (9976KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract Taking a certain subway station as the research object, this study employs model testing, numerical simu? lation, and on-site monitoring to conduct a comparative analysis of the stress characteristics of surrounding rock and support structures under two tunnel structure forms: the unidirectional arch and the dome (bidirectional arch) at the intersection section of the station's air duct and the main tunnel. The research findings indicate that the dome shape is more conducive to tunnel stability, with surrounding rock settlement reduced by approximately 7% compared to the unidirectional arch, and a smaller disturbance range to the surrounding rock. The stress state of the surrounding rock at the inner corner exhibits a trend of "three-dimensional-two-dimensional-one-dimensional" changes, leading to the formation of cracks that require close attention. The maximum tensile stress in the sprayed concrete layer is0.11 MPa, located at the inner corner of the intersection and at the cross-section between the intersection section and main tunnel. During the excavation of the lower bench, the axial force of the hollow grouting anchor bolts in the air duct and the main tunnel decreases, while the prestressed anchor bolts in the intersection section are almost unaffected. Additionally, the stress on the steel arch in this section is significantly asymmetric, with localized tensile stress occurring in the steel arch near the main tunnel side. Based on these findings, a "support first, break later"construction method is proposed, which involves first erecting an inner steel arch before dismantling the original steel arch support. On-site monitoring shows that the maximum settlement of the dome-shaped tunnel is approximately 5.2 mm, and the stress on the support structure remains within a safe range, ensuring the overall stability of the tunnel.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
WANG Mingfa1 LIU Guoshan1 YAN Jianquan2 MAN Xinjie1 LI Hongze2 ZHOU Yangyang1 LI Weiteng2GUO Guangming1 SHAO Xing3 JIANG Weiliang1
KeywordsIntersecting tunnel   Dome-shaped tunnel structure   Stress characteristics   Active support   Deformation     
Abstract: Taking a certain subway station as the research object, this study employs model testing, numerical simu? lation, and on-site monitoring to conduct a comparative analysis of the stress characteristics of surrounding rock and support structures under two tunnel structure forms: the unidirectional arch and the dome (bidirectional arch) at the intersection section of the station's air duct and the main tunnel. The research findings indicate that the dome shape is more conducive to tunnel stability, with surrounding rock settlement reduced by approximately 7% compared to the unidirectional arch, and a smaller disturbance range to the surrounding rock. The stress state of the surrounding rock at the inner corner exhibits a trend of "three-dimensional-two-dimensional-one-dimensional" changes, leading to the formation of cracks that require close attention. The maximum tensile stress in the sprayed concrete layer is0.11 MPa, located at the inner corner of the intersection and at the cross-section between the intersection section and main tunnel. During the excavation of the lower bench, the axial force of the hollow grouting anchor bolts in the air duct and the main tunnel decreases, while the prestressed anchor bolts in the intersection section are almost unaffected. Additionally, the stress on the steel arch in this section is significantly asymmetric, with localized tensile stress occurring in the steel arch near the main tunnel side. Based on these findings, a "support first, break later"construction method is proposed, which involves first erecting an inner steel arch before dismantling the original steel arch support. On-site monitoring shows that the maximum settlement of the dome-shaped tunnel is approximately 5.2 mm, and the stress on the support structure remains within a safe range, ensuring the overall stability of the tunnel.
KeywordsIntersecting tunnel,   Dome-shaped tunnel structure,   Stress characteristics,   Active support,   Deformation     
Cite this article:   
WANG Mingfa1 LIU Guoshan1 YAN Jianquan2 MAN Xinjie1 LI Hongze2 ZHOU Yangyang1 LI Weiteng2GUO Guangming1 SHAO Xing3 JIANG Weiliang1 .Analysis of the Stress Characteristics at the Dome Type Metro Tunnel Intersection[J]  MODERN TUNNELLING TECHNOLOGY, 2025,V62(1): 157-169
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2025/V62/I1/157
 
No references of article
[1] ZHANG Shan MENG Lubo QU Xiaoqi LI Tianbin ZHANG Yu.Experimental Study on the Deformation and Failure Mechanism of Red Sandstone under Groundwater Softening[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(1): 201-211
[2] CHEN Wang1 PENG Yanfeng1 LIU Weizheng2 ZHANG Siyu2 CHEN Changhui1.Analysis of the Impact of the Three Pipe Jacking Over-crossing Construction on Existing Tunnel and Surface Deformation[J]. MODERN TUNNELLING TECHNOLOGY, 2025,62(1): 170-182
[3] ZHANG Chengyou1 WANG Bo1 DU Zehao1 GAO Junhan1 TAN Lihao2.Analysis of the Suitability of Different Anchor Bolt Support Systems for Rockburst Mitigation and Optimization of Anchor Bolt Parameters[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(6): 64-73
[4] ZHANG Mingshu1 YAO Chen1 WU Xianguo2 CHEN Hongyu3 FENG Zongbao2 YANG Sai2.Deformation Prediction and Control for Shield Tunnelling Passing under Existing Tunnels Based on BO-Adam-Bi-LSTM[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(6): 92-99
[5] XUE Qingsong.Deformation Distribution Characteristics and Control Measures of Large-section Rectangular Pipe Jacking Over-crossing Metro Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(6): 148-161
[6] LIU Zhaoyang1 JIANG Kai2 LIANG Yu2,3,4.Settlement Analysis of Existing Prefabricated Subway Stations Induced by Overburden Backfill Load Based on Kerr Foundation Model[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 71-78
[7] LI Lijun.Analysis of the Impact of Excavation on Ground Settlement and Adjacent Pipeline Deformation Considering Spatial Variability of Soil[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 193-199
[8] SONG Yuepeng1 FAN Xiaofeng2 LIANG Yu2,3,4 PENG Hongguo5 ZHANG Hanwei5.Deformation Monitoring and Analysis during the Excavation of Deep Circular Shafts in Intercity Railway Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 219-226
[9] YANG Yi1,2 SHI Chenghua1,2,3 ZHENG Keyue1,2 PENG Menglong1,4 LOU Yili1,2.Research on Large Deformation Grading Control Technology for High Stress Red Layered Soft Rock Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(5): 252-262
[10] LV Linhai1,2,3 JIANG Mingjie1,2 XIE Zhongming1,2 HUANG Zhonghui4 WANG Binghua3 MEI Guoxiong5.Calculation Method for Underlying Tunnel Deformation Induced by Foundation Pit Excavation Based on Layered Mindlin Solution[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 95-104
[11] LIU Bo1,2 ZHENG Jinlei1,3,4 ZHANG Zhao1 MA Jianfei4.Study on Mechanical Model for Longitudinal Deformation of Existing Shield Tunnel Caused by New Tunnel Over-crossing Construction[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 112-118
[12] ZHU Meiheng1 CHEN Sirui2 HUANG Zhongkai2 LI Yongbo1 ZHANG Wuyu3 ZHANG Dongmei2.Study on the Deformation Law of Large-diameter Fully Prefabricated Assembled Shield Tunnels under Ground Surcharge[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(4): 161-171
[13] WANG Jianyu.“Resistance”or“Yielding”?Discussion on the Basic Concept for Dealing with Rock Squeezing Problems[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(3): 1-7
[14] HUAN Yuxiang1 TIAN Liyong2 YANG Wenbo1 LI Haoyu1 LIU Yong3 TANG Hao3 YAO Chaofan1.Study on Mechanical Behavior and Spatio-Temporal Deformation during Support Replacement in Soft Rock Large Deformation Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(3): 96-107
[15] ZHU Jianlin1 WANG Lichuan2,3 L IU Zhiqiang1 MA Liyao2,3 LI Qingbin2.Analysis on Action Mechanism of Multi-layer Support in Soft Rock Large Deformation Tunnels with Consideration of Rheological Effects[J]. MODERN TUNNELLING TECHNOLOGY, 2024,61(3): 18-24
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY