现代隧道技术 2023, Vol. 60 Issue (4) :178-187    DOI:
安全防灾与病害整治 最新目录 | 下期目录 | 过刊浏览 | 高级检索 << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
铁路隧道底鼓风险等级划分方法及控制措施研究
(1.中铁二院工程集团有限责任公司,成都 610031; 2.成都理工大学 地质灾害防治与地质环境保护国家重点实验室,成都 610059)
Study on Risk Level Classification Method and Control Measures for Railway Tunnel Floor Heave
(1. China Railway Eryuan Engineering Group Co., Ltd., Chengdu 610031; 2.State Key Laboratory of Geological Disaster Prevention and Geological Environment Protection, Chengdu University of Technology, Chengdu 610059)
Download: PDF (4033KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 高速铁路隧道仰拱底鼓问题会严重影响无砟轨道列车的运行速度及安全。为准确定量评价铁路隧道底鼓的风险程度,通过对国内多座铁路隧道底鼓变形的调研分析,结合未确知测度理论与改进层次分析法,对设计与运营阶段铁路隧道底鼓风险等级划分以及控制措施进行研究。考虑地质环境、隧道结构特征及底鼓特征等因素,在隧道设计阶段确定包含5个一级指标和11个二级指标的底鼓风险等级划分体系,在隧道运营阶段确定了包含6个一级指标和15个二级指标的底鼓风险等级划分体系;根据铁路隧道底鼓病害风险程度,铁路隧道底鼓风险等级分为Ⅰ、Ⅱ、Ⅲ和Ⅳ级,基于隧道底鼓风险等级以及各指标对底鼓的影响规律,建立了铁路隧道底鼓风险等级评价方法及流程;针对设计和运营阶段铁路隧道底鼓风险等级,建立了相应的底鼓控制综合措施。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
赵万强 1 路军富 2 汤 印 1 郑长青 1
关键词铁路隧道   底鼓   风险等级划分   判定指标   控制措施     
Abstract: In recent years, the invert floor heave problem in high-speed railway tunnels has become prominent, which has seriously affected the running speed and safety of trains on the ballastless track. In order to accurately and quantitatively evaluate the risk level of railway tunnel floor heave, a study is conducted on the classification of risk levels and control measures for railway tunnel floor heave during the design and operation stages through investigation and analysis of floor heave deformation of some railway tunnels in China and in combination with the unascertained measure theory and the improved analytic hierarchy process. The research results indicate that, considering these factors such as geological environment, tunnel structural characteristics and floor heave characteristics, a risk level classification indicator system of floor heave including 5 Level I indicators and 11 Level II indicators is determined in the tunnel design stage; another risk level classification indicator system of floor heave including 6 Level I indicators and 15 Level II indicators is determined in the tunnel operation stage; According to the risk degree of rail? way tunnel floor heave defects, the risk levels of railway tunnel floor heave are divided into Level I, II, III and IV.The risk level evaluation method and process of railway tunnel floor heave are established based on the risk level of tunnel floor heave and the influence law of each indicator on floor heave; corresponding integrated control measures are prepared for the floor heave risk levels of railway tunnels during the design and operation stages.
KeywordsRailway tunnel,   Floor heave,   Classification of risk levels,   Judgment indicators,   Control measures     
基金资助:国家自然科学基金面上项目(51978088);SKLGP国家重点实验室自主课题(SKLGP2021Z007).
作者简介: 赵万强(1970-),男,硕士,正高级工程师,主要从事隧道及地下工程方面的研究工作,E-mail:msxhb@126.com. 通讯作者: 路军富(1978?),男,博士,教授,主要从事隧道及地下工程方面的研究与教学工作,E?mail:luj
引用本文:   
赵万强 1 路军富 2 汤 印 1 郑长青 1 .铁路隧道底鼓风险等级划分方法及控制措施研究[J]  现代隧道技术, 2023,V60(4): 178-187
ZHAO Wanqiang1 LU Junfu2 TANG Yin1 ZHENG Changqing1 .Study on Risk Level Classification Method and Control Measures for Railway Tunnel Floor Heave[J]  MODERN TUNNELLING TECHNOLOGY, 2023,V60(4): 178-187
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2023/V60/I4/178
 
没有本文参考文献
[1] 张 欢1,2 张世殊3 李天斌1,2 杨 罡1,2 李世森1,2 肖华波3 陈卫东3.基于GAPSO-LightGBM的TBM施工隧道围岩等级智能预测方法[J]. 现代隧道技术, 2025,62(2): 98-109
[2] 匡 亮1 粟 威1 陶伟明1 田四明2 申玉生3 黎 旭2 汪辉武1.跨走滑断层隧道结构影响分区及设防范围研究[J]. 现代隧道技术, 2024,61(6): 45-54
[3] 魏荣华1,2 张康健1,2 张志强1,2.铁路隧道深埋水沟防排水技术参数优化研究[J]. 现代隧道技术, 2024,61(5): 183-192
[4] 宋越鹏1 范晓锋2 梁 禹2,3,4 彭红国5 张晗炜5.城际铁路隧道深大圆形竖井开挖阶段变形监测分析[J]. 现代隧道技术, 2024,61(5): 219-226
[5] 周晓军.基于横断面几何参数的高速铁路隧道预制拼装二次衬砌分块设计方法[J]. 现代隧道技术, 2024,61(4): 232-243
[6] 高树全1,2,3 蒋良文1,2,3 牟元存1,2,3 李 星1,2,3 王树栋1,2.西南复杂艰险山区铁路隧道超前地质预报技术[J]. 现代隧道技术, 2024,61(2): 52-59
[7] 王明年1,2 邓 涛3 于 丽1,2.中国交通隧道运营及防灾通风技术发展与展望[J]. 现代隧道技术, 2024,61(2): 152-166
[8] 曾弘锐1,2 孙文昊3 何 卫3 郭亚林1,2 郭 春1,2.基于机器学习的铁路隧道施工碳排放预测模型研究[J]. 现代隧道技术, 2023,60(6): 29-39
[9] 朱星宇 刘 征 张志强 冯 应.铁路隧道结构设计参数对二次衬砌裂缝影响规律研究[J]. 现代隧道技术, 2023,60(5): 1-10
[10] 陈 伟1,2 张明红2 张 莹2 林 玲2.中老铁路某隧道盐岩工程地质特征研究[J]. 现代隧道技术, 2023,60(5): 234-242
[11] 范文昊 1,2 谢盛昊 1,2 周飞聪 1,2 王志杰 1,2 张 凯 3 骆云建 3.新建双线盾构隧道下穿既有隧道近接影响分区及控制措施案例研究[J]. 现代隧道技术, 2023,60(4): 43-57
[12] 朵生君.铁路隧道TBM长距离施工通风技术研究[J]. 现代隧道技术, 2023,60(4): 222-228
[13] 张崇辉 梁庆国 孙纬宇 岳建平 张兴臣.考虑流变效应的泥岩隧道仰拱变形特征研究[J]. 现代隧道技术, 2023,60(4): 116-127
[14] 陈锡武 1 卿伟宸 1 刘国强 2.高地应力断层带超大断面隧道施工设计[J]. 现代隧道技术, 2023,60(4): 204-212
[15] 袁传保 1 鲁金林 1 陶玉敬 1 宋 章 1 刘国强 2.复杂强震山区跃龙门隧道重大工程地质问题研究[J]. 现代隧道技术, 2023,60(4): 188-195
Copyright 2010 by 现代隧道技术