现代隧道技术 2011, Vol. 48 Issue (4) :116-121    DOI:
施工技术 最新目录 | 下期目录 | 过刊浏览 | 高级检索 << [an error occurred while processing this directive] | [an error occurred while processing this directive] >>
宜万铁路齐岳山隧道629高压充水溶腔处理技术
(中铁十二局集团第二工程有限公司,太原  030032)
Techniques for Treating a High-pressure Water-filled Cavity in Qiyueshan Tunnel on Yichang-Wanzhou Railway
(2nd Engineering Company, China Railway 12th Engineering Bureau Group, Taiyuan  030032)
Download: PDF (0KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 在齐岳山隧道正洞DK363+629掌子面进行超前水平钻探时,揭示出前方存在一个大型腔体,随后实施超前探测,初步判断了腔体形状,对腔体进行了处理。首先对溶腔进行注浆试验,总计注浆1 613 m3,注浆效果不明显,掌子面停止注浆试验;注浆试验失败后,对DK363+629溶腔进行放水试验,放水量为3 000 m3/h,持续放水共计144 h,水量约43万m3,水压持续在0.2 MPa左右,由于受到外界降雨的影响水压持续上扬,证明腔体具有良好的地表联通性和水量补给持续性,为了保证施工安全停止了放水试验。平导贯通后可采用自然流出法排水,并对腔体采取“释能降压”施工。本次泄水总量约63万m3,水压自0.4 MPa降至0.0 MPa,水量稳定在约1 000 m3/h;随后对腔体实施爆破施工,爆破后采用管道引排的方法在不改变原有水流方向和不影响整体地下水系的情况下顺利通过。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
骆文学
关键词铁路隧道        高压充水溶腔        释能降压        放水试验        超前地质预报     
Abstract: A large cavity in karst was detected during exploratory horizontal drilling ahead of the face in the Qiyueshan tunnel at DK363+629. Exploratory borings were used to determine the shape of the cavity. An injection test was carried out for the karst cavity with a total injection volume of 1613m3, but the test was unsuccessful. A water discharge test was then conducted for the karst cavity with a water release volume of 3000 m3/h continuously for 144h. The water volume was estimated at 430 thousand cubic meters and the water pressure was around 0.2 MPa. The water pressure rose constantly due to rainfall, which showed that the cavity was connected to the ground surface with a continuous water supply. The water discharge test was stopped to ensure construction safety. Natural draining was adopted after breaking through the parallel adit and the principle of "energy releasing and pressure reduction" was followed. The total volume of discharged water was around 630 thousand cubic meters, and the water pressure was dropped to 0.0 MPa from 0.4 MPa, with a steady rate of water flow around 1000 m3/h. Finally, blasting was employed for the cavity and pipe draining was used without changing the direction of water flow and affecting the whole underground water system.
KeywordsHigh-pressure water-filled karst cavity,   Energy release and pressure reduction,   Water discharge test,   geological forecasting,   Railway tunnel     
出版日期: 2011-03-08
作者简介: 骆文学(1978-),男,工程师,从事隧道及地下工程施工技术工作,E-mail:luwenxue61@163.com
引用本文:   
骆文学 .宜万铁路齐岳山隧道629高压充水溶腔处理技术[J]  现代隧道技术, 2011,V48(4): 116-121
LUO Wen-Xue .Techniques for Treating a High-pressure Water-filled Cavity in Qiyueshan Tunnel on Yichang-Wanzhou Railway[J]  MODERN TUNNELLING TECHNOLOGY, 2011,V48(4): 116-121
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2011/V48/I4/116
 
没有本文参考文献
[1] 原先凡 1 廖 丹 2.基于 GOCAD的 TRT测试成果解译方法研究[J]. 现代隧道技术, 2019,56(3): 18-24
[2] 杨继华 1 梁国辉 2 曹建锋 2 杨风威 1.兰州市水源地建设工程输水隧洞 TBM1施工段关键技术研究[J]. 现代隧道技术, 2019,56(2): 10-17
[3] 智 鹏 史天运 王万齐 解亚龙.高速铁路隧道工程精益化建设管理关键技术[J]. 现代隧道技术, 2018,55(6): 26-32
[4] 汪波1, 郭新新1, 何川1, 吴德兴2.当前我国高地应力隧道支护技术特点及发展趋势浅析[J]. 现代隧道技术, 2018,55(5): 1-10
[5] 吴丰收 1,2 李 静 3 花晓鸣 1 李富明 1 卢 松 1.基于多源地震干涉法的隧道超前地质预报技术数值模拟研究[J]. 现代隧道技术, 2018,55(3): 92-97
[6] 刘兆勇 王羿磊 杨 威.相对坐标测量系统在 TRT法隧道地质超前预报中的应用[J]. 现代隧道技术, 2018,55(2): 146-151
[7] 唐曾智 1 田新成 1 夏沅谱 2 李二兵 2 谭跃虎 2.基于属性识别理论的隧道施工超前地质预报可靠性分析[J]. 现代隧道技术, 2017,54(4): 48-55
[8] 周 捷 席锦州.综合超前地质预报在新铜锣山隧道中的运用[J]. 现代隧道技术, 2017,54(4): 207-212
[9] 余世为 1 刘成禹 1, 2.基于地震波法测定岩体弹性抗力系数[J]. 现代隧道技术, 2017,54(1): 68-73
[10] 拓勇飞, 郭小红.南京纬三路过江通道总体设计与关键技术[J]. 现代隧道技术, 2015,52(4): 1-6
[11] 李昕1, 舒恒1, 张亚果2, 杨林松1, 李金1, 郭小红1.超高水压复合地层大直径盾构隧道纵断面优化设计研究[J]. 现代隧道技术, 2015,52(4): 7-14
[12] 姚占虎1, 杨钊2, 田毅1, 忽慧涛1.南京纬三路过江通道工程关键施工技术[J]. 现代隧道技术, 2015,52(4): 15-23
[13] 李新宇, 张顶立, 房倩, 宋浩然.越江跨海隧道突水模式研究[J]. 现代隧道技术, 2015,52(4): 24-31
[14] 舒恒, 吴树元, 李健, 郭小红.超大直径水下盾构隧道健康监测设计研究[J]. 现代隧道技术, 2015,52(4): 32-40
[15] 刘光凤1, 陈方伟2, 周直1, 张士龙3, 刘明强1.基于灰色模糊多属性群决策的越江隧道投资风险辨识[J]. 现代隧道技术, 2015,52(4): 41-48
Copyright 2010 by 现代隧道技术