硬岩隧洞小导洞法超前爆破开挖施工技术

Advance Blasting Excavation Techniques for Small Pilot Headings in Hard Rock Tunnels

  • 摘要: 某引水工程小断面硬岩隧洞原采用全断面钻爆法开挖,由于楔形掏槽深度受断面宽度限制,导致循环进尺较小,影响了施工进度。针对此问题,文章研究了小导洞超前、全断面光面爆破扩挖跟进的施工方法,并详细介绍了该施工方法的工序、掏槽方式、爆破参数及试验结果。试验结果表明:与常规全断面开挖方法相比,采用该施工技术可以较大地提高掘进速度、改善光爆质量、降低工程造价。

     

    Abstract: A water transfer tunnel in hard rock with a small cross section, which was originally constructed by the full-face drill and blast method, suffered from a low advance rate and affected the construction schedule since the depth of the wedge cut hole was limited by the section width. In light of this setback, a new construction method was proposed. First, the pilot heading is excavated by advance blasting, and then the tunnel is enlarged by smooth-blasting. This paper details the construction procedures, cut hole pattern, blasting parameters, and testing results regarding the new construction method. The results show that, compared with conventional full-face excavation, the new construction method increases the advance rate, improves smooth blasting quality, and reduces construction costs significantly.

     

/

返回文章
返回