巷道复合顶板分层厚度反演研究

Research on Stratified Thickness Inversion of Roadway Composite Roof

  • 摘要: 为了在只有顶板离层仪监测数据的情况下了解复合顶板各分层的厚度,进而确定坚硬分层的位置,文章以渝阳煤矿N3702运输巷支护失效段为工程背景,提出了反演复合顶板各分层厚度的方法。首先根据该巷道顶板离层仪的监测数据分析顶板离层空隙的位置及其离层量;然后将复合顶板简化为简支梁并推出其挠度方程,再结合顶板最大下沉量反演出第一分层泥岩的厚度;接着合理假设其余各分层厚度,应用组合分层的方式并结合顶板实际离层量从而最终反演出各分层厚度。现场试验结果表明:基于该方法反演的复合顶板各分层厚度而确定的坚硬分层位置对指导巷道支护参数优化效果显著,其中巷道试验段顶板下沉量较原支护减少了127 mm,顶板持续变形时间缩短了近25 d。

     

    Abstract: In order to understand the thickness of each layer of the composite roof and to determine the position of hard delamination in the case of only obtaining the monitoring data of roof delamination, a method for inversion of each layer thickness of composite roof was proposed based on the support failure section of N3702 transport lane of the Yuyang coal mine. In light of the monitoring data of roof delamination, the position of delamination void and the amount of delamination were analyzed; the composite roof was simplified as a simply supported beam and its deflection equation was deduced, and the first stratified mudstone layer was inverted combined with the maximum roof subsidence; the remaining delamination thicknesses were reasonably assumed, and each delamination thickness was inversed by combining compound stratification and the actual roof delamination. The field test results show that the hard stratified position determined by each stratification thickness of composite roof inversed by the proposed method can effectively optimize the parameters of roadway support, and the roof subsidence of test section is reduced by 127mm and continuous roof deformation is shortened by nearly 25 days compared with that of original support.

     

/

返回文章
返回