Comparison of Roof Brushing Construction Schemes for the Horizontal Adit and Main Tunnel of the Jieling Tunnel on the Yiba Expressway
1 Construction Headquarters of Yiba Expressway Directorate, Yichang 443700 2 China Railway 12th Bureau Group Co., Ltd, Yichang 443700
Download: PDF (0KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
Abstract The construction of the Jieling Tunnel on the Yiba Expressway was behind schedule due to complicated geological conditions that required prolonged treatments of collapse areas. In this case it was decided to add horizontal adits in order to modify the exposed working face. In this article, the two schemes of construction technology for horizontal adits are introduced and an analysis and comparison of the schemes of vertical passing and curved transition are addressed in terms of technical feasibility and economic viability.
Service
Email this article
Add to my bookshelf
Add to citation manager
Email Alert
RSS
Articles by authors
Keywords:   
Abstract: The construction of the Jieling Tunnel on the Yiba Expressway was behind schedule due to complicated geological conditions that required prolonged treatments of collapse areas. In this case it was decided to add horizontal adits in order to modify the exposed working face. In this article, the two schemes of construction technology for horizontal adits are introduced and an analysis and comparison of the schemes of vertical passing and curved transition are addressed in terms of technical feasibility and economic viability.
Keywords:   
Cite this article:   
.Comparison of Roof Brushing Construction Schemes for the Horizontal Adit and Main Tunnel of the Jieling Tunnel on the Yiba Expressway[J]  MODERN TUNNELLING TECHNOLOGY, 2012,V49(3): 146-153
URL:  
http://www.xdsdjs.com/EN/      或     http://www.xdsdjs.com/EN/Y2012/V49/I3/146
 
No references of article
[1] LIU Shihao1 SONG Zhanping1,2,3 XU Leilei4 XIA Zhenzhao5 WANG Junbao1,2,3.Optimization of Method Statement for Low-carbon Tunnel Construction Based on SVM-MAUT[J]. MODERN TUNNELLING TECHNOLOGY, 2023,60(6): 68-79
[2] HUANG Peng1,2 WEI Liangwen1,2 ZHANG Xuefu1,2.Study on Reinforcement of Large Arch Foot of Mined and Overlapped Metro Transfer Stations[J]. MODERN TUNNELLING TECHNOLOGY, 2021,58(6): 137-147
[3] YANG Jian1,2.Comparison and Selection of Construction Methods for Changsha-Ganzhou High-speed Railway Tunnel Section Adjacent to the Runway of Huanghua Airport[J]. MODERN TUNNELLING TECHNOLOGY, 2021,58(2): 118-126
[4] LIU Yi1,2 HE Zuhao1,3 WANG ZhiMin1 MA Chao1,2 LIU Wen1,3.Research on Roof-ripping Construction Technology for Tunnels under Fractured Surrounding Rock Conditions[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(6): 200-206
[5] TANG Xie1 LIN Guojin1, 2 HE Jia1 WANG Jun1.Design and Practice of Auxiliary Construction Scheme for Micangshan Tunnel Using Ventilation Shaft[J]. MODERN TUNNELLING TECHNOLOGY, 2020,57(4): 12-19
[6] Yan Tao1,2, Wang Mingnian1, Guo Chun1, Chen Hanbo1, Xie Wenqiang1.Key Techniques for the Diffused Oxygen Supply of an Extra-Long Highway Tunnel in a High-Altitude Area[J]. MODERN TUNNELLING TECHNOLOGY, 2015,52(2): 180-185
[7] LI Guo-Liang, SI Jian-Jun, Li-Ning.Construction Scheme of the West Qinling Extra-Long Tunnel on the Lanzhou-Chongqing Railway [J]. MODERN TUNNELLING TECHNOLOGY, 2014,51(3): 7-14
[8] Zhang Zhigang Hu jinping Liu Hongzhou Xu Guoping.Study of the Maximum Longitudinal Gradient of Underwater Highway Tunnels[J]. MODERN TUNNELLING TECHNOLOGY, 2013,50(4): 8-14
[9] Zhou Wenbo.Discussion of the Application of Extra-Large Diameter EPB Shields
to Road Tunnels in Central Urban Areas
[J]. MODERN TUNNELLING TECHNOLOGY, 2013,50(3): 1-7
[10] TANG Xie-1, Li-Hai-Qing- 2, LIN Guo-Jin-1, Tian-Shang-Zhi-1.Key Techniques for the Design of the Gaoersi Extra-Long Single-Tube Tunnel on the Sichuan-Tibet Highway[J]. MODERN TUNNELLING TECHNOLOGY, 2012,49(6): 108-115
[11] LIU Ming-Gao.Analysis and Research of a New Tunnel Over-passing an Existing Railway Tunnel with Short Distance[J]. MODERN TUNNELLING TECHNOLOGY, 2012,49(5): 79-84
[12] LIU Guo-Qing-1, WANG Guang-Hong-2.Design Optimization of the Upward Transition Section from the Inclined Shaft to the Taoshuping Main Tunnel in Water-Rich Sandstone Stratum[J]. MODERN TUNNELLING TECHNOLOGY, 2012,49(4): 69-75
[13] HE Cheng-1, WU De-Sheng-2.Geological Prediction Methods of Expressway Tunnel on Yinxiu Epicenter[J]. MODERN TUNNELLING TECHNOLOGY, 2012,49(3): 182-185
[14] MU Rui.Study of Ground Settlements Induced by the Construction of a Pipe-Roof Tunnel under a Highway[J]. MODERN TUNNELLING TECHNOLOGY, 2012,49(3): 104-108
[15] WANG Ming-Hui, JIANG Shu-Ping.Comparative Study of Deep Cutting and Tunnel Options on Mountain High-speed Railway[J]. MODERN TUNNELLING TECHNOLOGY, 2012,49(1): 1-6
Copyright 2010 by MODERN TUNNELLING TECHNOLOGY