PBA工法地铁车站下穿桥梁方案优化研究
(1北京中咨正达交通工程科技有限公司,北京 100029; 2清华大学水利水电工程系,北京 100084; 3 吉林大学交通学院,长春 130022)
On Scheme Optimization of the PBA Subway Station Underneath a Bridge
(1 Beijing ZZZD Traffic Engineering Technology Co. Ltd., Beijing 100029; 2 Department of Hydraulic Engineering, Tsinghua University, Beijing 100084; 3 College of Transportation, Jilin University, Changchun 130022)
Download: PDF (0KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要  文章以北京地铁6号线花园桥站下穿花园桥为工程背景,采用FLAC3D数值模拟和层次分析法确定PBA工法(Pile-Beam-Arch Method) 地铁车站下穿桥梁的最优方案,并结合监测结果分析了关键施工阶段对地层和桩基的影响。研究表明,同等注浆加固条件下4导洞法控制远、近侧桩基位移效果比5,6导洞法稍好,相同车站施工方法和结构型式下对近侧桥桩区域适当注浆加固和大范围注浆加固效果相近,因此,确定5导洞法及近侧桥桩区域内适当注浆加固为最优方案;导洞开挖、扣拱和其它工序地表沉降比例为0.38∶0.32∶0.30;导洞开挖和扣拱对近侧桩基位移影响较大,站台层开挖对远侧桩基沉降影响最大,导洞开挖和扣拱影响次之,但对水平位移影响较大。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
韦京1
王芳2
孙明志3
关键词:   
Abstract: Based on the Huayuanqiao station of Beijing Metro Line 6, which passes under the Huayuan bridge, an optimal scheme for the subway station, which is constructed by the Pile-Beam-Arch (PBA) method, is determined by FLAC3D numerical simulation and the analytic hierarchy process (AHP). The impact of key construction stages on the stratum and pile foundation is analyzed in conjunction with the monitoring results. The research shows that: the effects of the four-heading method on control of the pile foundation displacement at the far and near sides is better than that of the five/six-heading method under the same grouting reinforcement conditions; the effects of the appropriate grouting reinforcement on the bridge-pile area at the near side is similar to that of wide-range grouting reinforcement if the construction methods and structures of the stations are the same; after comprehensive consideration, a five-heading method with appropriate grouting reinforcement is determined to be the optimal scheme; the ratio of surface subsidence of the heading excavation, buckle arch, and other construction procedures is 0.38∶0.32∶0.30; construction of the heading and buckle arch has a large impact on pile foundation displacement at the near side; and excavation of the platform has the most serious impact on pile foundation settlement at the far side, with heading excavation and the buckle arch taking second place (the latter greatly affects horizontal displacement).
Keywords PBA construction method,   Subway station,   Passing under a bridge,   Adjacent pile foundation,   Numerical simulation,   Analytic hierarchy process     
出版日期: 2014-09-18
作者简介: 作者简介: 韦 京(1988-),女,硕士研究生,主要从事隧道及地下工程方面的研究工作,E-mail:water963@yeah.net.
引用本文:   
韦京1, 王芳2, 孙明志3 .PBA工法地铁车站下穿桥梁方案优化研究[J]  现代隧道技术, 2014,V51(6): 101-107
WEI Jing-1, Wang-Fang-2, Sun-Ming-Zhi-3 .On Scheme Optimization of the PBA Subway Station Underneath a Bridge[J]  MODERN TUNNELLING TECHNOLOGY, 2014,V51(6): 101-107
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2014/V51/I6/101
 
没有本文参考文献
[1] 刘飞香 1,2.SCDZ133智能型隧道多功能作业台车及其施工技术[J]. 现代隧道技术, 2019,56(4): 1-7
[2] 周文波 吴惠明 赵 峻.泥岩地层常压刀盘盾构的掘进策略与分析[J]. 现代隧道技术, 2019,56(4): 8-15
[3] 陈卓立 1,2 朱训国 1,2 赵德深 1,2 王云平 1,2.深埋隧洞让压支护结构的锚固机理探究[J]. 现代隧道技术, 2019,56(4): 16-22
[4] 王全胜.矩形盾构法隧道管片分块案例分析及分块原则[J]. 现代隧道技术, 2019,56(4): 23-29
[5] 张 恒 1 朱亦墨 1 林 放 1 陈寿根 1 杨家松 2.基于Q系统的地下洞库中台阶最佳开挖高度研究[J]. 现代隧道技术, 2019,56(4): 30-37
[6] 李 好.大断面岩溶隧道贯通段地质情况的无线电波透视试验探测[J]. 现代隧道技术, 2019,56(4): 38-42
[7] 岑培山 1 田坤云 2 王喜民 3.蒙华铁路阳山隧道瓦斯危害性评估研究[J]. 现代隧道技术, 2019,56(4): 43-49
[8] 朱建峰 1 宫全美 2.软土地层盾构隧道长期沉降离心试验研究[J]. 现代隧道技术, 2019,56(4): 49-55
[9] 陈柚州 1 任 涛 2 邓 朋 2 王 斌 3.基于人工蜂群优化小波神经网络的隧道沉降预测[J]. 现代隧道技术, 2019,56(4): 56-61
[10] 王登茂 滕振楠 田志宇 陈志学.桃园至巴中高速公路八庙隧道非常规岩爆段病害处治与设计反思[J]. 现代隧道技术, 2019,56(4): 62-68
[11] 吴树元 1 程 勇 1 谢全敏 2 刘继国 1 陈必光 1.西藏米拉山隧道围岩大变形成因分析[J]. 现代隧道技术, 2019,56(4): 69-73
[12] 王 睢 1,2,3 钟祖良 3 刘新荣 3 吴 波 1,2,4 赵勇博 1,2 李占涛 1,2.基于D-P准则有压圆形衬砌隧洞弹塑性解[J]. 现代隧道技术, 2019,56(4): 74-80
[13] 李 明 严松宏 潘春阳 张旭斌.富水大断面黄土隧道开挖流固耦合效应分析[J]. 现代隧道技术, 2019,56(4): 81-88
[14] 张 凯 1 陈寿根 2 霍晓龙 3 谭信荣 4.岩溶地区隧道涌水风险的可拓评价模型及应用[J]. 现代隧道技术, 2019,56(4): 89-96
[15] 李 杰 1 张 斌 1 付 柯 1 马 超 1 郭京波 1 牛得草 2.基于现场掘进数据的复合地层盾构掘进性能预测方法研究[J]. 现代隧道技术, 2019,56(4): 97-104
Copyright 2010 by 现代隧道技术