玉希莫勒盖隧道温度场及保温层厚度的研究
(1 山东科技大学山东省土木工程防灾减灾重点实验室, 青岛 266590; 2 中国矿业大学深部岩土力学与地下工程国家重点实验室, 徐州 221116)
Study on the Temperature Field and Insulation Layer Thickness of the Yuximolegai Tunnel
(1 Shandong Provincial Key Laboratory of Civil Engineering Disaster Prevention and Mitigation, Shandong University of Science and Technology, Qingdao 266590; 2 State Key Laboratory For Geomechanics & Deep Underground Engineering, China University of Mining& Technology, Xuzhou 221116)
Download: PDF (2543KB)   HTML (1KB)   Export: BibTeX or EndNote (RIS)      Supporting Info
摘要 新疆 G217国道玉希莫勒盖隧道位于高海拔季节性冻土地区, 为确保隧道运营的安全性, 需对其温度场及保温层厚度进行研究。针对这一问题, 文章首先采用自动温度监测仪对该隧道进行现场观测, 得到隧道不同径向深度处的温度变化规律; 通过室内试验测定相关计算参数, 并根据现场温度监测的拟合分析结果确定模型边界条件, 将该隧道未铺设保温层时的温度场计算结果与现场温度监测结果进行对比, 可以看出两者变化趋势基本吻合;然后进一步分析现场采用 5 cm保温层的可靠性, 计算结果表明, 在衬砌壁后仍存在 0.4 m的冻结范围; 同时分析了冻结锋面的扩展规律, 得出拱肩和底板是冻结锋面扩展速度最快、 距离最远的部位, 视为整个断面的危险位置; 最后以拱肩和底板处衬砌外侧的温度是否为 0℃作为判据计算了该隧道所需保温层厚度。文章研究成果对高山季节性寒区隧道的建设具有一定的指导意义。
Service
把本文推荐给朋友
加入我的书架
加入引用管理器
Email Alert
RSS
作者相关文章
冯 强 1 刘炜炜 1 蒋斌松 2
关键词:   
Abstract: The Yuximolegai tunnel on the G217 national highway in Xinjiang is located in a high-altitude seasonal frozen-ground region. In order to ensure its safe operation, it is necessary to study its temperature field and determine a proper insulation layer thickness. An automatic temperature monitor was used to obtain temperature variations at different radial depths of the Yuximolegai tunnel. Based on the calculating parameters determined by laboratory tests, the model boundary conditions were determined by fitting the analytical results of field temperature monitoring. The temperatures obtained by field monitoring were compared with those determined by the temperature field calculation without an insulating layer, and their changing tendencies are basically in agreement. Further analysis was conducted on the reliability of the 5 cm-thick insulating layer used in the field, and the calculations show that there is a freeze scope of 0.4 m behind the lining wall. The expanding law of the freezing front was analyzed and results indicate that the freezing front expands fastest and for the farthest distance on the spandrel and bottom, where the most dangerous positions on the whole cross section are. Ultimately, the required thickness of the insulating lay? er was calculated according to the criteria of whether or not the temperature outside the spandrel and bottom lining layer is 0℃.
KeywordsTunnels in a seasonal cold region,   Temperature field,   Field monitoring,   Freezing front,   Insulating layer     
基金资助:

基金项目: 国家自然科学基金(51508314);中国博士后科学基金(2016M59221); 山东科技大学人才引进科研启动基金(2015RCJJ061).

作者简介: 作者简介: 冯 强(1985–), 男, 博士, 讲师, 主要从事岩石力学理论与工程应用的研究工作, E-mail: fqcumt@163.com.
引用本文:   
冯 强 1 刘炜炜 1 蒋斌松 2 .玉希莫勒盖隧道温度场及保温层厚度的研究[J]  现代隧道技术, 2016,V53(5): 78-84
FENG Qiang- 1 Liu-Wei-Wei- 1 Jiang-Bin-Song- 2 .Study on the Temperature Field and Insulation Layer Thickness of the Yuximolegai Tunnel[J]  MODERN TUNNELLING TECHNOLOGY, 2016,V53(5): 78-84
链接本文:  
http://www.xdsdjs.com/CN/      或     http://www.xdsdjs.com/CN/Y2016/V53/I5/78
 
没有本文参考文献
[1] 刘飞香 1,2.SCDZ133智能型隧道多功能作业台车及其施工技术[J]. 现代隧道技术, 2019,56(4): 1-7
[2] 周文波 吴惠明 赵 峻.泥岩地层常压刀盘盾构的掘进策略与分析[J]. 现代隧道技术, 2019,56(4): 8-15
[3] 陈卓立 1,2 朱训国 1,2 赵德深 1,2 王云平 1,2.深埋隧洞让压支护结构的锚固机理探究[J]. 现代隧道技术, 2019,56(4): 16-22
[4] 王全胜.矩形盾构法隧道管片分块案例分析及分块原则[J]. 现代隧道技术, 2019,56(4): 23-29
[5] 张 恒 1 朱亦墨 1 林 放 1 陈寿根 1 杨家松 2.基于Q系统的地下洞库中台阶最佳开挖高度研究[J]. 现代隧道技术, 2019,56(4): 30-37
[6] 李 好.大断面岩溶隧道贯通段地质情况的无线电波透视试验探测[J]. 现代隧道技术, 2019,56(4): 38-42
[7] 岑培山 1 田坤云 2 王喜民 3.蒙华铁路阳山隧道瓦斯危害性评估研究[J]. 现代隧道技术, 2019,56(4): 43-49
[8] 朱建峰 1 宫全美 2.软土地层盾构隧道长期沉降离心试验研究[J]. 现代隧道技术, 2019,56(4): 49-55
[9] 陈柚州 1 任 涛 2 邓 朋 2 王 斌 3.基于人工蜂群优化小波神经网络的隧道沉降预测[J]. 现代隧道技术, 2019,56(4): 56-61
[10] 王登茂 滕振楠 田志宇 陈志学.桃园至巴中高速公路八庙隧道非常规岩爆段病害处治与设计反思[J]. 现代隧道技术, 2019,56(4): 62-68
[11] 吴树元 1 程 勇 1 谢全敏 2 刘继国 1 陈必光 1.西藏米拉山隧道围岩大变形成因分析[J]. 现代隧道技术, 2019,56(4): 69-73
[12] 王 睢 1,2,3 钟祖良 3 刘新荣 3 吴 波 1,2,4 赵勇博 1,2 李占涛 1,2.基于D-P准则有压圆形衬砌隧洞弹塑性解[J]. 现代隧道技术, 2019,56(4): 74-80
[13] 李 明 严松宏 潘春阳 张旭斌.富水大断面黄土隧道开挖流固耦合效应分析[J]. 现代隧道技术, 2019,56(4): 81-88
[14] 张 凯 1 陈寿根 2 霍晓龙 3 谭信荣 4.岩溶地区隧道涌水风险的可拓评价模型及应用[J]. 现代隧道技术, 2019,56(4): 89-96
[15] 李 杰 1 张 斌 1 付 柯 1 马 超 1 郭京波 1 牛得草 2.基于现场掘进数据的复合地层盾构掘进性能预测方法研究[J]. 现代隧道技术, 2019,56(4): 97-104
Copyright 2010 by 现代隧道技术