天目山隧道通风与施工环境有害气体组分实时监测研究

Ventilation and Real-time Monitoring of the Harmful Gas Components during the Construction of Tianmu Mountain Tunnel

  • 摘要: 钻爆法隧道施工期间会产生大量的有害气体,因此通风与卫生防护非常重要。文章以杭州—黄山高铁天目山隧道为例,通过对爆破后环境空气质量进行实时监测,对比通风前后有害气体浓度变化,分析有害气体组分时空分布规律,评价通风效果。研究结果表明:爆破后按稀释内燃机械排放废气所需风量(2 688 m3/min)通风 15min后,隧道内环境空气质量达标,各作业班次有害气体组分均不超标,通风效果良好。

     

    Abstract: Lots of harmful gas release during tunnel construction by D&B method, and the ventilation and health protection during the tunnelling process is of great significance. Taking the Tianmu Mountain tunnel on the Hangzhou-Huangshan high-speed railway as the background, real-time monitoring of air quality after blasting was conducted and concentration variations of harmful gas before and after ventilation were compared to analyze the timespatial distribution law of the components of harmful gas and evaluate the ventilation effect. The results show that the air quality meets the standards after ventilation for 15 min with a volume of 2 688 m3/min required by dilution of exhaust gas emitted by internal-combustion engines, and the harmful gases do not exceed the standards for all the working shifts, which proves good ventilation effect. The results provide significant guidance for the environmental air quality control and health protection during tunnelling.

     

/

返回文章
返回